| Road
Science
How to Manage Concrete Road Life
Cycles
Research points to using excellent mixes as a
starting point.
by Ruth W. Stidger, Editor-in-Chief
Concrete road life cycles range from 20 to 60 or more
years. Often, well-designed roads make it to 40 or more years with minimal
maintenance. It’s all in the basics of design and construction, the
experts report.
When restoration is needed, some techniques extend the
life of concrete pavement up to nine times their original design life,
according to the Northeast Chapter of the American Concrete Pavement
Association.
With good management, concrete roads cost 25 to 50% less
to maintain than asphalt, according to the same group.
Design and life
Many road designers expect a 30- to 35-year life cycle
for concrete pavements. Working with the American Concrete Pavement
Association, the Innovative Pavement Research Foundation set up a
seven-year plan to improve both the concrete road design life and
maintenance to extend the complete life cycle. Some projects began in 1998
and have been completed. The entire program will be finished in 2005.
Research areas include pinpointing today’s best
practices, reducing initial costs without compromising concrete pavement
performance, reducing road user delays during construction or maintenance,
developing cost-competitive concrete pavement options, and increasing
concrete pavement design life.
Finding the right mix greatly affects design life. This
includes portland or blended cement and supplementary materials such as
fly ash, chemical admixtures, aggregates, and water.
Good quality aggregates in a variety of sizes let the
designer use less water and cement, yet improve concrete life, says mix
expert, Jim Shilstone from Dallas.
Most U.S. departments of transportation use only local
aggregates, but Australian agencies often haul good aggregates 100 miles
or more, offsetting hauling costs with the resulting lower cement
expenditures.
Traffic and life
Heavy traffic, particularly heavy truck traffic, can
affect pavement life. In Canada, the Nova Scotia Department of
Transportation and Public Works carried out a five-year study to determine
which concrete technologies provide the best pavement life for residential
streets, collectors, arterials, expressways, and freeways.
The study started by comparing the structural
characteristics of rigid (concrete) and flexible pavements.
Flexible pavements rely on the asphalt, base, and
subbase layers to transfer the applied load, the NSDOT reports.
|

|

|
|
Typical Flexible and Rigid Pavement Layers |
Rigid or concrete pavements do not require the base or
subbases for structural strength and subgrade strength is not a critical
element in the thickness design, according to the study. Subgrade has
minor impact on overall thickness in terms of structural design, but is a
consideration for drainage.
|

|

|
|
Typical Load Distribution for Flexible and
Rigid Pavement Layers |
The study, which compared adjoining portland cement
concrete pavement and asphalt pavement, looked at profile ride index,
riding comfort index, surface friction, noise data, cost of repairs and
maintenance, and distress survey information.
Quick reconstruction
When concrete pavement does need repair, it can be done
quickly, contrary to popular beliefs that concrete materials are slow
curing.
Researchers at the University of California in Berkeley
documented a reconstruction project on Interstate 10 in California — 1.6
miles of concrete pavement was replaced in 55 hours over one weekend by
the Morrison-Knudsen Corporation. The work included lift-out and haul-away
of slab segments previously sawcut; clean cement-treated subbase;
installing tiebars and dowels; placing, finishing, and texturing the new
concrete; curing for four hours; sawing joints; and opening to traffic,
according to the Innovative Pavement Research Foundation, who reported on
the project in conjunction with the Federal Highway Administration.
The segment of I-10 running through southern California,
commonly called the San Bernardino Freeway, was built in the early 1960s
for a 20-year design life. Traffic volumes in this stretch of freeway are
high, as much as 240,000 average daily traffic with about 9% heavy trucks.
Time and traffic had taken their toll on the old pavement, resulting in
extensive slab cracking and joint faulting.
To document the effort, the Innovative Pavement Research
Foundation hired researchers at the University of California at Berkeley.
The research objectives included the documentation of the traffic
management plan and construction process for both nighttime and weekend
closures, to track the techniques the contractor used to reconstruct the
urban concrete pavement, and to identify which construction areas were
constraining the overall project productivity. Identification of the
constraining activities could help improve future construction
productivity by allowing contractors and agencies to focus on innovations
in a particular area.
The replacement of 1.7 lane miles used fast-track
concrete with four-hour curing time and was completed successfully in 55
hours. This indicates that state agencies should be confident of at least
that amount of pavement reconstruction during a weekend.
Concrete delivery to the site was found to be the
constraining factor. The overall progress of the project was found not to
be controlled by the demolition activities, the maximum amount of the
demolition under the contractor’s process for 55 hours of work could
have handled a 3-lane-mile project. Likewise, concrete cure time was not a
significant limiting factor.
If the initial paving progress had been maintained
throughout the project with no breakdowns, the maximum amount of
rehabilitation which could have been completed within a 55-hour weekend
would be 2.1 instead of 1.7 lane miles.
Opening it up
Concrete roads subject to heavy rains can have increased
life cycles with pervious concrete use. This material is a porous concrete
surface that lets rain and stormwater through it rather than flooding the
road, surrounding area, or storm drains.
Pervious concrete is only one element of a porous paving
system, warns Charger Enterprises, a pervious concrete contractor in
Seminole, Florida. Other needed elements include a suitable base soil,
proper preparation of a compacted, well-drainable subbase, a suitable mix
design, and correct mixing, placement, finishing, and curing.
What makes a good installation:
1. Soil evaluation, according to Charger Enterprises.
Test borings will establish whether soil will support the subbase and
pervious soils that contain significant levels of silt or clay that are
either highly compressible, lack cohesion, or expand or contract with
moisture absorption. These may not be suitable for concrete pavement
unless remediation steps are taken to stabilize the soil.
2. Base preparation. Before concrete is placed, the
subbase must be compacted using a vibratory or other suitable piece of
equipment to achieve a minimum density of 90 to 95%. The compacted base
must be done prior to the placement of paving material, but no puddles of
free-standing water can be tolerated.
3. Mix design. According to Charger Enterprises,
pervious mixtures must use high-quality control. They contain portland
cement, a nominal 0.375-inch Florida limerock aggregate, and admixtures as
designed. Almost all fine aggregate is eliminated from the mix to provide
the necessary voids to allow penetration of water. Typically, pervious
concrete has about 70% of the density of standard concrete paving
mixtures. The amount and timing of the addition of water to the mix is
critical. Too much water will carry the cement slurry to the base of the
pavement, creating a barrier that prevents water from passing into the
subbase and substrate. Too little water prevents bonding of the aggregate
to the cementitious mixtures.
4. Replacement. The subbase must be compacted to
specification. Ruts created by equipment or vehicles prior to placement
must be eliminated and recompaction used. Forms must be built to specified
grades. Rail-mounted leveling equipment should be aligned and placed prior
to beginning placement. The material should be discharged from the trucks
as rapidly as possible and feasible. In leveling, the paved area must be
rolled immediately, using a full-length roller and supplemental compaction
if needed.
5. Curing. Following placement, the pervious concrete
should be covered with polyethylene film, which should be held down
securely. Curing time without traffic is seven days.
Air-entrained concrete, where thousands of microscopic
air bubbles are introduced, lets the pavement material withstand the
effects of freeze/thaw cycles.
Also called foamed or cellular concrete, the material is
made from mixing preformed stable foam to a slurry of cement, sand, and
water to create enclosed air bubbles.
The material is especially suited for road bases and
bridge abutments.
FASTFACT
Concrete pavements can be reused both for road
surfaces and bases, with the entire operation accomplished on site.
FASTFACT
Because of its light color, concrete reflects from 33 to
50% more light than asphalt and can lower a city’s temperature by
several degrees.
Fastfact source: Northeast Chapter of the American Concrete
Paving Association.
Reprinted from Better Roads Magazine
April 2002 |