-
178 structures had randomly dispersed
low-density cracks — not an urgent concern but could get worse.
-
180 had medium-density cracks, mostly near
supports. They need frequent monitoring and must either be restricted or
replaced in the near future.
-
129 bridges had widely dispersed high-density
cracks. They also need frequent monitoring and must either be restricted
or replaced in the near future.
In the meantime, an investigation of the additional
300 RCDG bridges owned by cities and counties showed that a medium to high
density of cracks had developed on 122 of these bridges.
Separately, as a result of Oregon’s observations of
cracking, the FHWA surveyed other states to determine whether they were
experiencing similar problems with their reinforced concrete deck girder
bridges. “The FHWA concluded from this survey that the type of cracking
observed in Oregon is not unusual, but the large number of bridges in Oregon
with such cracks is exceptional,” wrote John E. Breen, P.E., chairman, TRB
Committee for Review of the Oregon Department of Transportation Study on
Bridge Shear, in a report issued June 2005 (see below).
Cracks disrupt commerce
Nearly 200 bridges identified for repair and
replacement were on I-5, the major north-south highway which runs from
Washington State to California, connecting every major city in the state.
Another 66 bridges were on I-84, which crosses the northeast corner of the
state from Washington to Idaho.
Worse, the problem was replicated on state highways
throughout Oregon. By the end of 2003, it was estimated that one out of
every five state-owned bridges was to require weight restrictions, and truck
detours. Without new funding, it was estimated in 2003 that nearly one out
of every three state-owned bridges would be weight limited by 2010. The
total estimated cost to repair all deficient bridges was $4.7 billion.
Symbolic of the impact on residents was the
experience of Riddle, Oregon, one of the first communities to be impacted by
the weight restrictions. As described in Oregon DOT’s Updated Economic and
Bridge Options Report, April 2005, for 20 days in March 2001, the
communities of Canyonville and Riddle, 30 minutes south of Roseburg,
experienced a surge in truck traffic unlike anything they had seen before.
Ford’s Bridge, an I-5 bridge several miles away, was closed for emergency
repairs, and the truck detours ran through the main streets of these two
towns of fewer than 1,500 people.
The streets and bridges of these two small
communities were not built to handle the volume of large trucks, resulting
in safety concerns and infrastructure damage to city facilities. The detours
had a negative effect on local commerce, not to mention lifestyles. For
example, Hayes Oil of Medford continued hauling 80 truckloads of gas and oil
per week using the detour routes. Depending on which detour they took, Hayes
added 100 to 200 miles per trip.
The Oregon DOT put the Ford’s Bridge project on a
fast track, making repairs to the bridge that were expected to last three to
five years, and got the trucks back on I-5 for the short-term. With funding
from the resulting Oregon Transportation Investment Act, the Oregon DOT
began construction of a replacement bridge in August 2002.
The funding problem was such that in March 2003,
Representative Peter DeFazio (D-Oregon) organized a letter signed by the
entire Oregon House delegation, and sent it to the leaders of the House
Transportation and Infrastructure Committee, asking that state funding to
help repair Oregon’s numerous cracked and crumbling bridges be matched in
the future surface transportation bill to replace the existing TEA-21.
“The State of Oregon cannot fix the cracked bridge
problem entirely on its own, which is why we are asking for assistance from
the federal government to help Oregon meet this need,” DeFazio and the
Oregon House delegation said.
Ultimately, DeFazio — the ranking Democrat on the
House Highways, Transit and Pipelines Subcommittee — was able to obtain
funds when TEA-21’s successor, the Safe, Accountable, Flexible, Efficient
Transportation Equity Act: A Legacy for Users, was passed and signed by
President Bush last year.
In SAFETEA-LU, a new funding category was added,
dubbed Megaprojects. To receive funding, a Megaproject must have national
and regional significance. Under this new category, DeFazio secured $160
million for reconstruction of bridges on I-5 in Oregon and $40 million for
reconstruction of bridges across the state.
To further leverage Oregon’s local funds, DeFazio
secured language in SAFETEA-LU that lowers the local match for most
transportation projects listed in the bill for Oregon. When federal dollars
are used for a project, the standard funding split is usually 20% local to
80% federal. But because Oregon supports a large amount of federal lands,
and thus has a smaller tax base, DeFazio was able to alter the legislation
to cut the local share in half, to 10.27%, with the federal share at 89.73%,
applying to all high priority projects and Megaprojects included in the
bill.
HB 2041 to rescue
In anticipation of having to repair or replace state
bridges, ODOT launched a Statewide Bridge Assessment in February 2003. The
purpose of this assessment was to collect environmental and engineering
baseline data at each bridge site identified in the 2003 Economic and Bridge
Options Report, verify the repair or replacement recommendation for each
bridge made in the 2003 report, and refine the scope of work and cost
estimates for repairing and replacing bridges, including identification of
engineering, construction, and right-of-way costs for each project.
Then, in response to the emerging bridge cracking
problem, the Oregon Legislature passed House Bill 2041 in 2003. The bill
provided $1.3 billion in funding to repair and replace bridges on Oregon’s
state highways. An additional $300 million was earmarked for repair or
replacement of county and city bridges, with another $361 million for county
and city operations and maintenance.
The package also allocated $500 million in
modernization projects, and was promoted as a jobs creator as well as a
means to mitigate bridge woes. This is Part III of the Oregon Transportation
Investment Act, which the legislature passed in 2001; Part III included a
budget note that directed the state to contract with the private sector to
assist the agency with the management of the OTIA III State Bridge Delivery
Program.
The result was in April 2004, the Oregon DOT
contracted with Oregon Bridge Delivery Partners, a private-sector firm that
is assisting the agency with managing the $1.3-billion state bridge program.
OBDP is a joint venture formed by HDR Engineering
and Fluor Enterprises, and provides day-to-day support to the OTIA III State
Bridge Delivery Program, ensures quality projects at least cost, and manages
engineering, environmental, financial, safety, and other aspects of the
program.
Detailing beats crack width
The diagonal cracking in beams noted by inspectors
has been associated with inadequate shear capacity, a situation engineers
design to avoid because it may lead to a sudden failure, reported Oregon
DOT’s Research News in late 2005.
But subsequent research funded by Oregon DOT and
conducted by Dr. Chris Higgins at Oregon State University at Corvallis at
its O.H. Hinsdale Wave Research Laboratory showed that repeated traffic
loading — regardless of the condition of the concrete — was not causing the
steel reinforcement to gradually deteriorate. This was a critical
consideration in deciding whether to replace or repair a bridge.
The research confirmed that Modified Compression
Field Theory (MCFT) accurately predicts concrete shear strength. Based on
the research recommendations, ODOT decided to apply the AASHTO Load and
Resistance Factor Rating (LRFR) method, which employs MCFT, as a basis for
decisions to repair rather than replace many of its cracked bridges that
were originally slated for replacement.
“They poured beams of the same reinforcement details
and sizes as we had in the 50s, and broke them in the lab,” Groff told
Better Roads. “We got great value out of their study. We have implemented a
lot of its provisions. We’ve learned, for example, that where the crack
looks the biggest, is not where the bridge may fail. It often may fail
somewhere else. Dr. Higgins’ tests showed that the mechanism for failure
does not necessarily follow the place where the biggest crack was early on.
Crack width is less important than what we used to think it was. What’s more
important, Higgins found, was the detailing of the rebar inside, including
anchorage of the longitudinal bars, or how far into the support they go.
What matters is detailing, not crack width.”
For this research, the OSU Civil, Construction &
Environmental Engineering Department was awarded nearly $1.6 million to help
the state analyze the severity of cracks.
The research also defined an accurate method to
estimate the load capacity of the cracked girders, which was incorporated
into a reliability-based procedure to load rate the cracked bridges, the
state said. Subsequent efforts have focused on implementing the load rating
method for cracked girders, repairing cracked girders, developing an
analysis method for cracked bent caps, and deploying bridge monitoring
technology.
OSU’s strong floor
The test facility, OSU’s strong floor, is the second
largest structural testing floor on the West Coast, and allows researchers
to simulate earthquakes and forces up to one million pounds, and frames up
to two stories high. The floor, measuring 24-feet wide and 68-feet long, is
steel-reinforced concrete, 5-feet thick, with massive bolts and anchors to
which materials can be attached and their strength tested.
On the strong floor, researchers can test, at full
scale, new high-performance materials, innovative connectors, and seismic
energy dissipating devices, as well as different configurations of
traditional steel and concrete materials that might be used to provide more
efficient or economical structures. The new facility aids research on bridge
girders, bridge decks, beam column connections, shear walls, and other
structures used in constructing buildings, bridges, and infrastructure.
“Without our new strong floor laboratory, ODOT would
have gone out of state to conduct this research,” said Higgins, an associate
professor in the College of Engineering.
To be practical, the load rating method developed
for the cracked bridges requires automation, the Oregon DOT said in late
2005. “Computer software is being developed at OSU to perform the
reliability-based assessment on RCDG bridges,” ODOT said. “An initial load
rating software package has been completed and a second generation package
is being developed that will provide more flexible analysis capabilities and
enhanced visualization modules.”
OSU’s findings are contained in two reports,
Remaining Life of Reinforced Concrete Beams with Diagonal-Tension Cracks (SPR
341, Higgins, Yim, et al. 2004), and Assessment Methodology for Diagonally
Cracked Reinforced Concrete Deck Girders (SPR 350, Higgins, Miller, et al.
2004).
OSU investigates repair methods
Repair methods for the bridges also are being
investigated at OSU, including epoxy injection, supplemental steel stirrups,
post-tensioning, and fiber reinforced polymer composites. “Large-scale
laboratory specimens cracked and repaired are loaded with increasing
amplitude until failure to determine the increase in shear capacity,” the
state said in its Fall 2005 Research News publication. “The effect of
repeated loading to simulate traffic on the behavior and performance of the
different repair methods is [being] evaluated. The research includes
investigation of in-service repaired RCDG bridges. This effort will provide
accurate methods of predicting the increase in capacity for specific repair
types, determine the longevity of repairs, and recommend effective repair
approaches optimized for the diagonal cracking prevalent in Oregon’s vintage
RCDG bridges.”
In addition, OSU is looking at cracked bent caps.
Bent caps are transverse beams that support the main girders. “Though
generally more heavily reinforced than girders, bent caps are non-redundant
and could potentially cause a bridge to collapse if one were to fail,”
Oregon said in 2005. “Many of Oregon’s 1950s-vintage RCDG bridges have
cracked bent caps along with cracked girders. Because of the relative
dimensions of bent caps, the analytical method for estimating load capacity
of cracked girders may not be accurate for bent caps. Consequently, OSU is
conducting research on large-scale bent caps in the laboratory to evaluate
the capacity and estimate the remaining life of cracked bent caps.”
Monitoring and acoustic analysis
Because monitoring a damaged bridge — in conjunction
with reduced load rating — can provide additional comfort that a bridge will
perform as expected, Oregon is investigating ways to monitor conditions in
real time. The state has contracted with Engineered Monitoring Solutions to
install a demonstration structural health monitoring system on four RCDG
bridges with cracked girders. The system will send strain and crack size
data to DOT personnel, along with alerting engineers to any sudden changes
in the condition of the bridge due to an overload.
In addition to bridge monitoring using conventional
technology, a joint research project between the Oregon DOT, OSU and
Portland State University is investigating acoustic emission testing as
another tool for determining the health of bridges.
According to the state research group led by Steve Lovejoy, ODOT
senior mechanical engineers, in AE monitoring, the sound given off by damage
is detected and characterized by the AE system. This research will develop a
protocol for applying AE testing to RCDG bridges in order to assist in
bridge element rating, setting load restrictions, and predicting the rate of
damage progression.
AE testing hears the sound given off by the material
when it is damaged, and has been shown to be a highly sensitive method for
detecting damage in experiments conducted on reinforced concrete beams, the
Oregon DOT said. “This research will develop a protocol for applying AE
testing to RCDG bridges with diagonal tension cracks in order to assist in
bridge element rating, setting load restrictions, and predicting the rate of
damage progression.” A manual for applying AE to reinforced concrete deck
girder bridges will be developed.
A critique by TRB
OSU’s work in recreating the bridge components of
the 50s and conducting destructive testing on them answered some major
questions for the Oregon DOT, but drew some pointed critiques by a
Transportation Research Board committee, which issued its opinions in June
2005.
FHWA requested a review of the results of the OSU
study by an independent panel of experts, and the Oregon DOT contracted with
the Transportation Research Board for an independent peer review of the OSU
findings.
The committee found that the OSU analysis, field
studies, and laboratory tests that conclusively indicated fatigue of web
reinforcement not to be a problem were convincing and followed sound
principles. It acknowledged that Oregon obtained a great deal of highly
useful documentation and information from OSU, and ODOT officials told the
committee that they believed that OSU had satisfied their expectations.
But it also found that OSU did not avail itself of
many essential components of basic AASHTO standards for load rating and
design, such as load factors and resistance factors, did not treat loads and
resistances as time-dependent variables, and did not provide clear guidance
for assessing the effects of reinforcement details. “The methodology did not
emphasize the use of nondestructive evaluation or invasive materials
sampling to enhance assessment of bridge remaining life,” wrote John E.
Breen, P.E., committee chairman, Ferguson Structural Engineering Laboratory,
University of Texas at Austin.
The Peer Review Panel also concluded that ODOT’s
re-evaluation of OTIA III bridges was based on nationally approved methods,
and that no bridges would need to be re-evaluated in light of the Peer
Review.
“OSU suggested we use Modified Compression Field
Theory, which is in use in the newest codes, such as LRFR code. It’s a newer
method of assessing shear capacity, and it accounts for the interaction of
longitudinal bars along the girder, and transverse bars, or stirrups. It’s
more sophisticated than the previous ACI method. You can get more capacity
out of the MCFT, and it represents a more realistic approach to capacity.”
Groff said.
Regardless of the critique, the OSU study paid off
for the Oregon DOT. “We got enormous value out of the OSU study, even though
some points of it were criticized,” Groff said.
Research continues in 2006
The Oregon DOT and its Research Unit continued to be
focused on bridge conditions in 2005, said Oregon DOT’s Research,
Development & Technology Transfer Program in its 2005 annual report, and the
work will continue this year.
The focus continues on the remaining life of the
generation of the 500 reinforced concrete bridges constructed 45 to 60 years
ago, Oregon’s research unit said. “The level of our research effort on
topics related to this issue was unprecedented,” the research unit said late
last year. “Nearly $1.5 million was spent on research projects in this area
in FY 2004 and FY 2005, and we anticipate spending more than $600,000 in
Fiscal 2006. That level of investment is approximately one third of our
total research effort.” |