August 2002
Back to Article Index

Better Bridges

CalTrans Rebuilds Sacramento River Bridge

Partners go fishing for ways to protect the environment
 and come up with a better bridge design.

by Karen Stidger, Contributing Editor

In the northern-most reaches of the central valley of California, less than 100 miles south of the Oregon border, the California Department of Transportation is reconstructing a 600-foot bridge on Interstate 5 which crosses the picturesque Sacramento River. A little more than a third completed, the three-year, $16.1-million CalTrans project boasts a modified California bulb-tee design, the first of its kind to be used in California. The unique design, consisting of sectional precast girders made continuous, is the result of addressing a litany of construction and environmental constraints.

The original parallel five-span hybrid steel girder bridge, built near the City of Anderson in the early 1960s as part of the completion of I-5 from Mexico to Canada, suffered from fatigue and critical scour. CalTrans knew replacing this bridge would be a difficult and lengthy task. A joint constructability review process was used to troubleshoot and discuss all foreseeable issues prior to design and work.

After two years of design planning and the bidding process, on February 20, 2001, CalTrans, District 2, awarded a three-year, three-stage contract to Shasta Constructors, Inc. of Redding, California.

Bridging the challenges

River protection. Minimizing the footprint to the pristine upper Sacramento River is key. This effort includes protecting the fisheries along with migratory birds that nest on the sides of the bridge, as well as maintaining clean water in accordance with The Clean Water Act.

The largest river in California, the Sacramento River runs through Anderson on its 381-mile serpentine path through the central valley on its way to the San Francisco Bay. Anderson is home to Coleman National Fish Hatchery, the largest salmon hatchery in the lower 48 states. Large numbers of fish are released into the rivers in the Anderson area to eventually return for spawning.

Seasonal runs of Chinook and Steelhead drive the bridge construction schedule, limiting in-river time to a window of May 1 through October 15 each year. In addition, precautionary methods used during demolition prevent debris from falling down into the river.

In spring, great numbers of swallows build their mud nests on the sides of the bridge where the river provides a diet of flying insects. To avoid interrupting the swallows’ mating season, nets are hung on the sides of the bridge, forcing swallows to seek other nesting locations before nests are built.

Because of sediment and alkaline by-products from concrete, water from cofferdams cannot be redeposited directly into the river. Instead, during the dewatering process, water is pumped into desilting basins where it is cleaned and neutralized before being returned to the river.

River access. Starting May 1, an access pad of spawning gravel is built halfway across the river. By October 15, phase work must be completed and the gravel removed from the river. At the end of the project, fishery overseers have requested that 58 cubic meters of spawning gravel be left behind in the river. Over time, the water currents will wash the gravel down the river to create natural spawning areas.

Bridge load. According to Mark Darnall, resident engineer for CalTrans, “Structural capacity and concerns about the existing bridge placed constraints on both design and physical placement of girders on the new bridge.” Each individual span has three girder segments, put into place by 100-ton cranes.

Highway traffic. Throughout the project, CalTrans maintains traffic flow at normal capacities without stoppages. However, certain steps, such as girder erection and pile driving require greater construction area access, making traffic diversion necessary. During these construction phases, Shasta performs work at night when traffic flow is lightest and when limiting traffic to one lane each way causes the least amount of disruption to drivers.

Noise pollution. The night work of pile driving creates extra noise pollution for the surrounding residential areas. In each stage of construction when noise levels are highest, Shasta notifies local residents and offers them substitute lodging at local motels. Only a small number of residents found it necessary to accept the contractor’s offer.

River traffic. In addition to maintaining normal highway traffic, river access for law enforcement, fishermen, and rafters is preserved by limiting the size of the gravel access pad in the water.

The replacement structure

Darnall reports the new bridge includes the following elements:

1. Pre-cast, pre-stressed Modified California bulb tee girders.

2. Segmental erection of four 47-meter spans, made continuous by post-tensioning.

3. 156 segments — three segments per span per girder.

4. High-strength concrete, 8,700 psi. The project requires a pumpable, flowing, high early strength mix using an M.B. Rheobuild 300 high-range water reducer.

5. Eight-foot steel pipe foundation, driven below the floor of 30-foot cofferdams.

6. Two-stage longitudinal post-tensioning, before and after deck placement.

7. Transverse post-tensioning at pier diaphragms before deck concrete pour.

8. Three piers instead of four, providing less obstruction in the water.

Three-stage construction

Each of the three stages in this project builds a double-lane bridge. Stage one, started in April 2001, called for the construction of a two-lane highway between the existing parallel bridges. The stage-one highway provides lanes for traffic diversion during the subsequent two stages. In the event of future highway expansion, the final bridge makes six lanes available.

On May 1, 2001, Shasta Constructors started work in the river with the building of the gravel access pad. From the completed access pad, construction of the substructure and temporary girder supports was carried out. Crews dug 30-foot cofferdams and drove piles into the riverbed. Shasta Job Superintendent Randy Smith recalls the challenge of digging through volcanic tuff with a long-armed excavator with pointed teeth.

Next, Tremie Seal was pumped to the bottom of the cofferdams, water was pumped from the coffers to the desilting basin, and crews trimmed the piles.

Once 100-ton cranes placed the concrete girder segments on the complete piers, the closures and diaphragms were poured. A local cabinet shop fabricated custom forms for the closures.

Longitudinal and transverse stressing made the girders self-supporting so that the falsework and access pad could be removed from the river by the October 15 deadline. When one deadline extension was required, the crews found themselves working in high water as river levels were raised to accommodate fall salmon runs.

Finally, the deck was poured and the final longitudinal path stressed.

The second stage replaces the northbound bridge while diverting northbound traffic to the stage-one lanes. During the demolition, the contract requires a registered engineer to be on site at all times. Shasta brought in Robert D. Prahl, retired CalTrans senior bridge engineer, as a consultant. When the deck was removed to expose the 40-year-old girders, Prahl said, “I was surprised the steel girders rebounded to their original camber. Even the paint was still pretty much intact.”

In 1962, Prahl was CalTrans assistant bridge engineer on the original Sacramento River Bridge project. The $5-million project included 24 bridge structures and the sub base for the I-5 roadway covering the 13-mile stretch between the cities of Anderson and Redding. Prahl retired from CalTrans as senior bridge engineer in 1998.

Stage three, scheduled to begin May 1, 2003, will replace the southbound bridge, switching southbound traffic to the stage-one lanes. Finally, all three stages will be transverse tensioned together and the railing and roadwork will be completed.

The estimated completion date for the Sacramento River Bridge is August 2004. In the meantime, thousands of truck drivers, motorists, and fishermen will hardly have noticed all the work, and the needs and concerns of a long list of partners will have been met.

Darnall, who values the constructability review process highly, comments, “Open communication with all parties involved helps to ensure a successful project.”

Reprinted from Better Roads Magazine
August 2002

 

Click Here to return to article index

Copyright © 2002 James Informational Media, Inc.
All rights reserved.

Home/Site Map
 
Buyers Guide
Supplier/Equipment
Information
Products
Top Products & More!
Industry Links
Associations, Suppliers,
DOT's, Counties
Article Archive
A popular Starting Point
Articles and News
Event Calendar
Trade Shows/Exhibits
& Events
RoadFax Forms
On-Line inquiry form
Advertising
Rate Card,
Advertising Information
Circulation
Subscription Form
Editorial
Editorial Calendar,
Submission Guidelines
Search  Classifieds Contact Us