August 2004
Back to Article Index

by Greg Garrett

Rehabilitating Michigan’s Paint River Bridge 

Rehabilitation using a reconstruction staging scheme and other factors made the project work.

Designer lighting adds to the bridge's classic look.

The Paint River Bridge is beautiful and very unique. One of only a handful of open-spandrel arch bridges, it is the sole non-redundant open-spandrel concrete arch bridge in the state.

The bridge, originally constructed in 1929, is also designated as an historic bridge, which adds to the complexity of the design and planning process.

The Michigan Department of Transportation entrusted the URS Corporation architects, engineers, and planners to design the rehabilitation and provide construction assistance for the two-span structure. URS Corporation was the sole design consultant for this project.

The historic two-span structure, located in Crystal Falls, a small town in Michigan’s scenic upper-peninsula, was built with a total length between abutment reference points of 261 feet, 10 inches.  Each span is 120 feet between arch spring points and consists of 22 spandrel columns, 11 on each of the two arch ribs.

 The original bridge possessed two 12-foot lanes plus a 5-foot sidewalk on each side of the structure and expansion joints in the deck at every other spandrel column. The expansion joints have been leaking for some time, causing deterioration to the deck slab and supporting spandrel columns resulting in the need to replace the superstructure. The bridge superstructure, including the deck slab, sidewalk, and spandrel columns was in need of replacement down to the arch ribs.

Rehab starts

The rehabilitation consisted of devising a reconstruction staging scheme, designing the new superstructure to match the original design while meeting current structural specifications, and, where possible, improve drainage and geometric characteristics of the bridge and approaches.

The structural characteristics for an arch bridge of this type preclude the normal approach to its demolition and reconstruction. This structure contains two arch ribs, or two main structural members for each span, deeming the bridge non-redundant.

If the structural integrity of either arch rib in a span is compromised structurally, impending collapse is possible. The removal or addition of any part of the superstructure during the demolition or reconstruction process drastically affects the stresses in the arch ribs. Thus, an in-depth structural investigation was necessary to evaluate the demolition and reconstruction staging processes.

A three-dimensional finite element model of the bridge was created to evaluate the stresses in the arches of the bridge throughout the construction process.  Many possible staging schemes were evaluated with each staging scheme requiring numerous finite element models. A typical model would include representative loading patterns of the bridge during a certain stage of the demolition or reconstruction process, and construction vehicle placement and/or movements.

Environmental effects were also a consideration when devising the staging scheme. To preserve the pristine Paint River and immediate surroundings around the bridge, the staging scheme would have to keep all large construction vehicles on the bridge or road approaches. This requirement ultimately led to staging the reconstruction of one span at a time due to limits on crane and concrete-pump truck reach.

Once a staging scheme was developed, plans were created for the staging and included in the final plan set. The final scheme was viewed as a starting point for the contractor to work from, requiring future refinement and coordination between URS and the contractor.

The entire deck and sidewalks are fixed at the pier and allowed to expand or contract longitudinally from the pier, independently from the rest of the structure.

Structure improvements

The new superstructure was designed with several characteristics to improve drainage, geometry, and structural performance of the bridge. The existing concrete deck had leaking expansion joints located about every 21 feet, 2 inches along the length of the bridge. These expansion joints led directly to the deterioration of the bridge and were considered a design flaw in terms of future maintenance. It was proposed to remove them entirely for the new structure.

A new joint-less deck would create a problem, in that expansion and contraction forces generated from thermal movements of the deck would be transferred down through the spandrel columns into the arches. The design solution to this dilemma was to separate the deck slab from the spandrel columns and allow it to float on guided elastomeric bearings atop the spandrel columns.

The entire deck and sidewalks are fixed at the pier and allowed to expand or contract longitudinally from the pier, independently from the rest of the structure. To prevent independent lateral movements of the superstructure, galvanized steel pins penetrate galvanized slotted plates between the elastomeric bearings at each spandrel column. The slotted holes allow for only longitudinal movements of the superstructure.

The original profile of the bridge included a vertical curve with the point of vertical intersection located at the pier. The PVI for the new structure was raised, resulting in a top-of-deck elevation at the pier, 3-inches higher than existing for improved water movement off the structure. The new concrete deck cross-slope was also increased to meet current standards.

The original structure carried two 12-foot lanes of opposing traffic. A large portion of the current traffic consists of oversized logging trucks or manufactured home carriers, which may cause the typical motorist to feel somewhat cramped in certain traffic situations. To help eliminate the tight, constrictive feeling at the bridge, 2 feet were added to the curb-to-curb clear distance of the bridge deck.

To accommodate the width increase, a combination of increasing the superstructure width 6 inches and decreasing the sidewalk width 6 inches on each side resulted in the net increase of 1 foot for each vehicle lane. The new sidewalks, with 6 inches less width, still meet current design standards and were accepted for the minimum pedestrian or snowmobile movements across the bridge. Use of current materials allowed for a thinner concrete deck resulting in a wider superstructure, but no increase in dead load, or weight applied to the arches.

Preserving details

Since the Paint River Bridge is on Michigan’s list of historic bridges, the designation requires any rehabilitation or reconstruction work to match the original with respect to appearance and/or materials. Design of the new superstructure had to match the original, while meeting current design standards.

The original structure included architectural railing and light pilasters along the sidewalk perimeter, but due to safety and maintenance concerns, the railing was replaced in the early 1970s with a less attractive substitute.

The historic nature of the structure required that any reconstruction match the original as closely as possible. Due to structural and safety concerns, reconstructing the original barrier railing was an issue.

To decrease forming and curing concrete time, precast concrete for several super-structure elements was recommended.

The solution to this quandary was to reconstruct the railing with the appearance of the original, but with structural improvements or additions, where needed. Structural steel tubes were added spanning between the railing pilasters in front of the concrete railing. These steel tubes act to transfer traffic accident “hit” loading to the concrete pilasters located every 10 feet, 7 inches along the sidewalk, and are invisible when viewing the bridge from the river or adjacent park.

The original appearance of the railing pilasters and light pilasters were also recreated, but designed with appropriate reinforcement to transfer loading down through the superstructure.

The non-functioning original lights and concrete light poles atop the pier and abutments act as the main architectural focus of the superstructure and seem to act as sentries for vehicles or pedestrians crossing the bridge. The new lights and light poles were designed to match the original in scale and appearance, but with a current electrical system and materials.

Precast concrete

The schedule for rehabilitating the bridge in one construction season was very restrictive for the contractor due to the extreme staging sequence. To decrease forming and curing concrete time, precast concrete for several superstructure elements was recommended.

The concrete transverse beams spanning between spandrel columns, hundreds of individual railing balusters, and light poles were all precast by the contractor, as recommended.

Precasting these elements also produced a superior product because fabrication tolerances are greater, environmental effects are lessened or eliminated, and forms may be used repeatedly when an element is shop cast and cured.

The transverse beams, for example, were cast, cured, and stored in a warehouse through the winter by the contractor. Thus, the beams had a better finish and attained a higher strength before being exposed to any loading due to curing the entire winter.

Approach improvements

The existing bridge approaches had a number of geometric and drainage deficiencies. When the bridge was originally built, the roadway standards were obviously developed to correspond to much lower design speeds and hydrology requirements.

The western approach had a horizontal curve just off the bridge with a deficient superelevation. The corrected superelevation of the new approach provides for much safer driving conditions, especially important for the large log trucks that tend to accelerate down the hill to the west when approaching the bridge.

The eastern approach also had geometric deficiencies in need of correction. The new approach was designed to provide adequate length for the lane width transition and proper vertical alignment by using an asymmetrical vertical curve.

During the design process the local MDOT and city authorities expressed concern about the occurring flush overflows every now and then in the vicinity of the bridge.

The bridge is located at the bottom of a steep sloped valley and experiences significant and sudden rain flows. Some of these have overflowed the curb line and caused erosion damage to the southwestern approach.

The new design included redundant drainage structures, spillway, and storm sewers, as well as full use of the existing storm system so that the flush-flow problem is resolved with an adequate drainage system.

This project demonstrates that it is possible to preserve the architectural history of our infrastructure while meeting the standards of today. A comprehensive study of this unique arch bridge was performed using the most modern engineering software tools available. This, coupled with modern materials and construction techniques not only reproduced significant architectural details, they were made much more structurally efficient, extending the life of this structure for decades.


Greg Garrett, P.E., is a structural engineer with URS Corporation, Grand Rapids, Michigan.

Reprinted from Better Roads Magazine
August 2004

Click Here to return to article index

Copyright © 2004 James Informational Media, Inc.
All rights reserved.

Home/Site Map
 
Buyers Guide
Supplier/Equipment
Information
Products
Top Products & More!
Industry Links
Associations, Suppliers,
DOT's, Counties
Article Archive
A popular Starting Point
Articles and News
Event Calendar
Trade Shows/Exhibits
& Events
RoadFax Forms
On-Line inquiry form
Advertising
Rate Card,
Advertising Information
Circulation
Subscription Form
Editorial
Editorial Calendar,
Submission Guidelines
Search  Classifieds Contact Us