August 2005
Back to Article Index

Better Bridges

Colorado Replaces Bridges Quickly

Using off-site construction and other techniques, Colorado’s Department of Transportation replaced two bridges with only 14 days of road closure.

by Mindy Crane

Last year, the Colorado Department of Transportation began what many people assumed was a typical bridge replacement project. However, most people didn’t realize that CDOT and its contractor, Lawrence Construction Company, were taking a unique approach to this project. This approach was done to reduce the impacts to traffic, protect the environment, and save taxpayers’ dollars.

The project called for the replacement of two 70-year-old, metal-truss bridges on U.S. 34 in the Big Thompson Canyon. This two-lane segment of U.S. 34 typically carries around 7,500 vehicles a day; however, during the summer, that number increases significantly as many tourists use this route to reach Rocky Mountain National Park. Furthermore, the roadway crosses over the Big Thompson River and is surrounded by hundreds of trees. Several businesses, residential communities, and an elementary school are also located near the project area.

Crews maneuver one of the girders into place during the first day of the 10-day closure.
Crews maneuver one of the girders into place during the first day of the 10-day closure.
One of the 70-year-old metal-truss bridges is lifted away from the roadway.

One of the 70-year-old metal-truss bridges is lifted away from the roadway.

Given the circumstances of the roadway and the surrounding area, CDOT realized many issues needed to be resolved. Under normal replacement procedures, detours would have to be constructed adjacent to each bridge.  The construction of the detours would have displaced about 200 trees and encroached upon wetland areas.  Pipes would also need to be installed for river flows, thereby adding silt to the river.

In addition, one of the sites would accommodate a detour for one-way traffic only, which would have required the installation of temporary traffic signals to regulate the traffic. The traffic signals would create delays for the traveling public as it would take at least five minutes for one direction of traffic to get through the construction zone and get the other direction moving. This detour would have been in place for several months, impacting the tourists as well as the many commuters in the area.

 “After reviewing the original replacement procedures, we realized that the situation was not ideal,” said CDOT Project Engineer Michael Command. “The environment was going to be greatly impacted and the traveling public would experience delays for many months. Knowing that the actual bridge replacement would take place in the summer, it was necessary to find an alternate plan.”

Quick replacement

With these concerns in mind, CDOT and Lawrence Construction worked together to devise a new plan. In the end, CDOT decided that the bridges would be replaced over a 10-day period, in which U.S. 34 would be completely closed for about 2 miles. Under this new procedure, a large portion of each bridge would be constructed off-site prior to the closure. Once the closure began, crews would deliver and place the sections of the bridges; thus, allowing for a quick bridge replacement procedure.

Once a plan was laid out, it was time to share the information with the traveling public. CDOT delivered flyers, mailed out letters, and met with the businesses and schools in the community in order to inform the public of the new construction plan. In addition, CDOT had to work with Larimer County officials to obtain permission to use the county roads for the planned detour route.

“One of the most challenging aspects of this project was getting the public to understand why a quick 10-day closure would be more beneficial than months of construction,” added Command. “After explaining the circumstances of the project, the community was on our side and ready for the closure to commence.”

How they did it

Under the new procedures, the project would begin in the spring of 2004 with the ground work while sections of the new bridges were constructed off-site. The preparatory work consisted of the construction of the caissons, columns, and abutments. This work took place through mid-June under minimal daytime lane closures. By mid-June, the majority of the preparatory work was complete and it was almost time for the bridge replacement to begin, but there was one problem. The tourist season was heading into full swing, which would mean greater impacts to the traveling public. As a result, CDOT elected to suspend the bridge replacement until mid-September when traffic was lighter.

After months of preparation, CDOT closed U.S. 34 and began the bridge replacement. With 40 workers prepared to take on the challenging task, the replacement got off to a great start. Within 24 hours, both bridges were removed.

Over the next few days, 16 girders were placed on one of the structures and placement got underway on the second structure. The placement of the girders on the second structure is where crews ran into some problems — the girders were not sitting squarely on the abutments. However, the problem did not hinder the process. Within a few hours, engineers determined it was necessary to shim the piers in order to level out the girders and the next step of the project was underway.

As work continued, it was apparent to the crews that the girders would not be their only problem. Towards the end of the fifth day, Mother Nature brought rain to the project, which softened the subgrade soil. Due to the time crunch, efforts were taken to haul in competent subgrade material so that paving could take place as quickly as possible. The softened soil, along with the girder issue, would delay the efforts, and the 10-day closure soon became a 14-day closure.

“CDOT was concerned with the delays brought on by the girders and soft soil which extended the closure,” said CDOT Resident Engineer Scott Ellis. “However, we decided that a quality project would more than make up for a few more days of inconvenience.”

Just when the crews thought the end was near, they encountered one last problem.  It was discovered that a rock fissure was allowing water to leak into the roadway subgrade near the upper bridge. Once again, CDOT engineers and the contractor put their heads together and designed a drain system to divert the water elsewhere.

Just five days after the decks were poured, U.S. 34 reopened to traffic with two new concrete box girder bridges that are safer for the traveling public. The upper bridge is now 149-feet long and 43-feet wide as opposed to 130-feet long and 35-feet wide. The lower bridge is 219-feet long and 43-feet wide, which is 54-feet longer and 8-feet wider than the old bridge. The extra width gives motorists and bicyclists more room and makes it easier for the two to share the road. Also, the new roadway alignment around the bridges enhances the site distance, making for a safer roadway.

Even though the bridges were completed in November 2004, the top mat of asphalt could not be placed because of the cold temperatures. Once the temperature warmed up, crews had to return to place the top mat of asphalt on both bridge decks. The paving was also conducted under minimal lane closures and was completed by April 2005.

The costs

The $2.6-million project that was scheduled to take a year and half to complete was actually completed several months ahead of schedule and with significantly less delays than originally expected.

“This project is a great example of how CDOT and its contractors work together to accomplish great things,” added Ellis. “Everyone on this project team worked together to overcome a difficult situation and in the long run, the traveling public and the environment benefited greatly. The hard work and innovation demonstrated in this project raises the bar for future transportation projects in Colorado.”


Mindy Crane represents the Colorado Department of Transportation.

Reprinted from Better Roads Magazine
August 2005

Click Here to return to article index

Copyright © 2005 James Informational Media, Inc.
All rights reserved.

Home/Site Map
 
Buyers Guide
Supplier/Equipment
Information
Products
Top Products & More!
Industry Links
Associations, Suppliers,
DOT's, Counties
Article Archive
A popular Starting Point
Articles and News
Event Calendar
Trade Shows/Exhibits
& Events
RoadFax Forms
On-Line inquiry form
Advertising
Rate Card,
Advertising Information
Circulation
Subscription Form
Editorial
Editorial Calendar,
Submission Guidelines
Search  Classifieds Contact Us