|
August 2005
Back to Article Index
|
 |
|
How States Preserve
Concrete Pavements
CPR pays off in extra pavement life.
by the Staff of the
American Concrete
Pavement Association |
|
From Georgia to the Pacific Northwest and California,
state transportation departments are recognizing that concrete pavement
restoration (CPR) is a cost-effective pavement preservation strategy.
And for good reasons. CPR provides several benefits that an asphalt
overlay cannot accomplish: CPR addresses the root cause of a pavement
distress, minimizing further deterioration. Covering a distress with an
asphalt overlay does not correct the real distress, which can manifest
itself again in the form of a larger, more expensive problem.
-
CPR costs less and lasts longer than an asphalt
overlay. CPR projects typically last between 7 and 12 years, and
some have performed for more than 17 years before a second
restoration.
-
CPR is quicker and causes less traffic
disruption. CPR repairs only those areas that need improvement, such
as the driving lane of a pavement.
-
CPR preserves the safety of concrete pavements.
With shorter joint spacing, load-transfer dowels,
and improved designs, today’s concrete pavements are designed never to
need CPR. But no pavement lasts forever, so we need CPR to preserve our
investment in concrete pavement. This article looks at CPR strategies in
Kansas, Missouri, Georgia, Texas, and Washington.
The Kansas experience
Kansas maintains about 1,100 centerline miles of
concrete pavement. Annually, the state does a distress survey of all its
pavements. “Normally, we don’t have to repair our concrete pavements,”
says Andy Gisi, a geotechnical engineer with the Kansas Department of
Transportation. “We can just build them and leave them alone.”
However, from 1976 to 1988, most of the state’s new
concrete pavements had no load-transfer dowels at the joints. “For about
the last five years, we’ve been doing dowel bar retrofitting and diamond
grinding on those pavements,” says Gisi. “If the faulting isn’t too bad,
we just do diamond grinding. We have just one more un-doweled project to
CPR, and then we’ll have completed all those projects.”
Lack of air entrainment in the concrete — caused by
human error — caused some longitudinal joint spalling in another Kansas
location. “For the spalling, we do partial-depth repairs,” says Gisi.
“We saw-cut to delineate the area, and the contractor can either use a
chipping hammer or a milling machine to remove the deteriorated
concrete.” That is followed by cleaning the hole, sandblasting it,
filling it with concrete, sawing the joint, and resealing it.
For some cracks, Kansas practices two types of
stitching. Diagonal holes can be drilled through the pavement section,
in the shape of an X across the crack. Epoxy and bars are then inserted
into the holes. Or with horizontal stitching, crews cut parallel slots
along a crack, remove the concrete, place bars in the slots, and grout
them back.
“We do horizontal stitching primarily in areas of
longitudinal cracking,” says Gisi. “Usually, that’s caused when the
contractor didn’t saw the joints soon enough after construction.” |
|
|
Kansas also does under-sealing, or slab stabilization.
If voids develop under a pavement, holes can be drilled through the slab
into the void. Crews then inject grout (fly ash, portland cement, and water)
or high-density polyurethane foam into the hole and under the slab. “We try
not to move the slab,” says Gisi. “If you’re not careful you can build
pillars into the slab. We’re just trying to fill the voids.”
If slab stabilization is not performed in time, serious
cracks can develop. They can call for full-depth repair or slab replacement,
Gisi says.
Dowel bar retrofits
In Texas, U.S. Route 287 was an un-doweled concrete
pavement with 60-foot joint intervals. An expansive clay sub-grade made
problems worse. Cracks and rocking slabs developed, and the state decided to
do CPR on a 4.9-mile stretch, in two lengths, in the towns of Childress and
Quanah. It is a five-lane pavement. For $3.2 million, the contractor, J.L.
Steele Incorporated, performed dowel bar retrofits, diamond grinding, and a
small amount of drum profiling (using a drum cutter).
The project was completed in September of 2004. “We’re
hoping to get 10 to 15 years more from that pavement,” says Ronald Hatcher,
district laboratory supervisor in the Childress District of the state DOT.
“The diamond grinding gave us a really good ride. It rides really well. We
got a very good job out of it.”
Long life in Georgia
About 5 to 7% of Georgia’s state road network consists
of concrete pavement, says A.J. Jubran, state pavements engineer with the
DOT. “Under the life cycle we assign to concrete pavements, we figure to get
20 years until the first CPR, then 10 years, then seven or five years,” says
Jubran. “It depends on the traffic, and whether or not the pavement was
overloaded. The state has one 5-mile section of Interstate 85, located near
South Carolina, that was built in the early 1960s and is “still in pristine
condition,” says Jubran.
Not long ago Georgia completed a $19.13-million project
on 14.7 miles of Interstate 75 south of Macon. Some $7.2 million of the cost
went for concrete pavement, and the project included lane replacement,
safety upgrades, and extensive CPR work. “We used full-depth slab
replacement, diamond grinding, and joint resealing,” says Myron Banks,
materials and research branch chief, Georgia DOT. “We reconstructed the
outside lane, but on the two interior lanes we did restorative work.” The
highway has eight lanes divided in one portion, and six lanes in another.
A second CPR-and-lane-replacement project, on Georgia’s
Interstate 85 in metro Atlanta, began in June last year and will continue
through November. One inside lane will be added, and the state will do CPR
on the two outside lanes. The existing pavement is three-lanes wide, and the
original inside lane needs no work. The 6.9-mile-long project will cost
$39.7 million.
Beefing up CPR
In Missouri, the past two years have seen the state DOT
add partial-depth repairs and dowel bar retrofits to its CPR bag of tricks,
says Mark Shelton, assistant state construction and materials engineer.
Before that, the state had specifications for full-depth repairs and diamond
grinding.
“Over the past two or three years, we’ve probably done
nearly 10 CPR projects,” says Shelton. “We’ve done projects with up to
several miles of diamond grinding. We regard CPR as a cost-effective way to
restore concrete pavements. The earlier you catch the pavement distresses
and do something about them, the more years you will get from the pavement.
“We saw some successes with partial-depth repairs and
dowel bar retrofits in other places, and those looked like technologies that
made sense for us,” says Shelton. To perfect the DBR techniques, Shelton
says the state worked with the Missouri-Kansas chapter of the American
Concrete Pavement Association. As for partial-depth repairs, Missouri
observed the success that Minnesota has had with that technology.
“On a lot of our contracts we do the PDR work ahead of
the diamond grinding,” says Shelton. For the partial-depth repairs we try to
identify areas that are still structurally sound but have spalling that’s
less than half-way through the pavement thickness.
“For dowel bar retrofits we do three saw cuts in the
wheel paths and use 1.5-inch dowels,” adds Shelton. “We like to use DBR
while transverse cracks are still in the early stages — while we still have
some load transfer due to aggregate interlock.
Current or recent CPR projects in Missouri include PDR
and DBR on Interstate 435 near Kansas City, and DBR and diamond grinding on
Interstate 370 near St. Louis.
Money for CPR
In Washington, the DOT has a budget for preserving
pavements, and, says pavement design engineer Jeff Uhlmeyer, “Obviously
concrete gets the least priority because it can last longer.” Still, the DOT
has identified needs for more than $400 million of CPR work.
Pavement surveys and evaluations show the need for 380
lane miles of DBR work, 230 lane miles of diamond grinding, and 530 lane
miles of reconstruction, says Nadarajah (Siva) Sivaneswaran, state pavement
management engineer. The DOT uses $330,000 per lane mile as the budgeted
figure for DBR work, which it has performed steadily since 1992.
CPR is expected to add 10 to 15 years of life to a
concrete pavement, Uhlmeyer says. “We don’t do asphalt overlays on concrete
pavements,” says Uhlmeyer. “DBR has been doing very well for us. Typically
we DBR the outside lane and diamond grind the inside lanes. You don’t have
to DBR all the inside lanes.”
Will the DOT get the money it needs for concrete
repair? In April, the state Senate was considering $406 million for existing
concrete pavements. The House had not publicized its proposal. “The $406
million only partially covers the need,” says Uhlmeyer. “All the lane miles
have been prioritized and broken into projects that we sent to both houses
of the legislature. We’ll see how much we get!” |
|
Found: A way to treat
diamond grinding slurry
The
Penhall Company, Minneapolis, recently found a solution to a challenge with
diamond-grinding slurry. The challenge is to dispose of the slurry formed
when the diamond blades’ cooling water mixes with the concrete cuttings from
the pavement.
California regulations make it very expensive to haul
away all of the wastewater and dispose of it off-site. “In California, it’s
tougher to get rid of that slurry,” says Casey Holloway, contracts manager
for Penhall.
The company has developed a method of treating the
slurry that Holloway says Caltrans initially “likes a lot.” This spring
Penhall found a chance to use the treatment method on a 141,000-square-meter
grinding project near Torrance, California. The project generated
1.7-million gallons of slurry, Holloway says, and it required three
4-foot-wide Cushion Cut grinders to complete. The job is located on six- and
eight-lane sections of Route 110, and all lanes need diamond grinding. To
avoid heavy traffic, work has been limited to the hours of midnight to 4:30
a.m.
Oil field technology
The slurry treatment equipment, sold by the Brandt
Company, closely resembles that used to treat drilling mud used in the oil
fields, Holloway says. The raw waste slurry first flows to a shaker screen
that scalps off the heaviest particles of concrete. From there, the slurry
drops into a 10,000-gallon agitator tank with paddles in it to keep the
concrete in suspension.
Next, the material is pumped to a 12,000-gallon
clarifying tank. Enroute to that tank, a polymer flocculant is added that
drops out the heaviest particles to the bottom of the tank. The heavy
material is pumped to a centrifuge, which consolidates it into a heavy
clay-like material.
“You come out with a material that’s about 10% water,”
says Holloway. It’s like a heavy clay. You can take it to a landfill. So
instead of 1.7-million gallons of slurry that we’d have to put in a hole or
in a berm, we’ll handle 100 end-dumps full of this clay-like and sandy
waste.”
As of spring, the little treatment plant was “doing a
good job of separating the material,” Holloway said. It may need a larger
centrifuge, however, to keep up with the project’s production. The plant can
be broken down and moved on two flat-bed trailers, and Penhall planned to
move it around to various projects. |
|
Standard Methods of
CPR
1. Slab stabilization. This technique restores
support to concrete slabs by filling small voids that develop underneath
the concrete slab at joints, cracks, or the pavement edge.
2. Full-depth repairs. This is a way to fix cracked
slabs and joint deterioration by removing at least a portion of the
existing slab and replacing it with new concrete.
3. Partial-depth repairs. These correct surface
distress and joint-crack deterioration in the upper third of the
concrete slab. Placing a PDR involves removing the deteriorated
concrete, cleaning the patch area, placing new concrete, and reforming
the joint system.
4. Dowel bar retrofits. This method consists of
cutting slots in the pavement across the joint or crack, cleaning the
slots, placing the dowel bars, and backfilling the slots with new
concrete. Dowel-bar retrofits link slabs together at transverse cracks
and joints so that the load is evenly distributed across the crack or
joint.
5. Cross-stitching longitudinal cracks or joints.
Cross-stitching repairs cracks that are in low-severity condition. The
method adds reinforcing steel to hold the crack together tightly.
6. Diamond grinding. By removing faulting, slab
warping, studded tire wear, and unevenness resulting from patches,
diamond grinding creates a smooth, uniform pavement profile.
7. Joint and crack resealing. This technique
minimizes the infiltration of surface water and incompressible material
into the joint system. Minimizing water entering the joint reduces
subgrade softening; slows pumping and erosion of the subgrade or subbase
fines; and may limit dowel-bar corrosion caused by deicing chemicals.
|
For more information, you can
contact the American Concrete Pavement Association headquarters at
847-966-2272. ACPA maintains chapter offices throughout the country that
stand ready to help with your concrete pavement questions. See also
www.pavement.com.
Reprinted from Better Roads Magazine
August 2005 |
Copyright © 2005 James Informational Media, Inc.
All rights reserved. |