August 2005
Back to Article Index

Paving a Half-Mile per Night in Georgia
Fast-tracked project opens concrete to traffic in a few hours.

by the Staff of the American Concrete Pavement Association

A recent project in Georgia has proven that you can open a new concrete pavement to Interstate traffic in just four to six hours after it is paved. Even though the concrete mix had to meet a strength of 2,500 psi in 24 hours, limited maturity data obtained by the contractor showed that the concrete achieved about 1,500-psi compressive strength at opening time — and could carry truck traffic — with no detrimental effects. Working about eight hours every night, the Ballenger Paving Division, APAC-Southeast Inc., removed one lane of old concrete pavement, paved an average of 1,500 feet per night, and reopened the new pavement to traffic by 10:00 a.m. the following morning. The 14.7-mile project took place on Interstate 75 near Macon, Georgia. The highway is a major route through Georgia and carries an average daily traffic of 54,000 with 24% trucks.

Ballenger replaced a 10-mile stretch of the 39-year-old outside lane on each side of the Interstate for a total of 20.1 lane miles of pavement. The remainder of the project was routine concrete pavement rehabilitation work. Total project cost was $19.1 million and the concrete pavement cost was $7.24 million. Work was completed on October 7, 2004.

The Ballenger Paving Division, APAC-Southeast, paved an average of 1,500 feet per night on I-75 near Macon, Georgia.
The Ballenger Paving Division, APAC-Southeast, paved an average of 1,500 feet per night on I-75 near Macon, Georgia.
For the fast-track paving, the contractor used an 8-bag mix, which gained strength to 1,200 to 1,500 psi in five and a half to six hours.

For the fast-track paving, the contractor used an 8-bag mix, which gained strength to 1,200 to 1,500 psi in five and a half to six hours.

On some nights, Ballenger was able to replace more than half a mile of pavement per night, says Wouter Gulden, director of engineering and training, Southeast Chapter, American Concrete Pavement Association. In fact, the contractor removed and replaced the 20.1 lane miles of concrete pavement in just 16 weeks time. The actual paving took the equivalent of 11 weeks and was done during the months of January through April 2004.

Drama at night

Beginning at 8:00 p.m. every night, the contractor closed down the two outside lanes, while the inside lane remained open, says Ronnie Ashmore, a vice president with Ballenger Paving Division, APAC Southeast. Work zone barrels came first, followed by sawing and removal of the old concrete. A wheel loader with forks removed 6- by 10-foot blocks of pavement. Next was smoothing and compaction of the existing base. Then Ballenger placed dowel baskets, chairs, and reinforcing mats.

Paving began about 10:30 or 11:00 p.m. Concrete was hauled from a central mixing plant to the site in Maxon side-dumps on Autocar trucks. The side-dumps emptied the concrete into a Maxon spreader, and a Gomaco 2800 slipform paver did the rest. Finishers used 16-foot straightedges to correct any minor deficiencies.

The contractor would stop paving each morning at about 4:00 to 4:30 a.m. The middle lane — used during construction as a safety buffer and haul road — had to reopen to traffic at 6:00 a.m. By 10:00 a.m., Ballenger could open the new pavement to traffic. The Georgia Department of Transportation specifies a minimum cure requirement time of four hours.

“This all required close coordination between the sawing and removal crews, the concrete plant, and the paving crew,” said Ashmore. “We at the Ballenger Paving Division had a work force of 75 people and the removal contractor had 25 people at the worksite. During a good portion of the night, all of the activities were taking place at once, from sawing the old slabs to paving the new concrete.”

High early strength

“Most fast-tracked concrete pavements are done during weekends,” says Gulden. “I don’t know of one done each night in concrete. It’s an equal production speed to deep milling of asphalt and repaving. The concept came out of the Georgia DOT’s Maintenance Office.

“Conventional wisdom says you need the 400-psi flexural strength or 2,500-psi compressive to hold up to trucks,” says Gulden. “But Georgia found in the late ‘70s that you can open it up sooner. And that was by trial and error. The Georgia DOT tried eight hours, and that worked, and then they tried six hours, and that worked okay. They get about 1,200 to 1,500 psi in five and a half to six hours.”

To achieve that strength, the Georgia DOT designed a high-early-strength mix with 750 pounds of Type 1 Portland Cement per cubic yard. It’s an eight-bag mix. “They added a non-chloride accelerator,” says Gulden. “It’s a standard paving mix except for the higher cement content and the non-chloride accelerator.

“The DOT’s challenge was to design a pavement system that had to be 10 inches in thickness to replace the existing slab,” says Gulden. “The existing slab was originally designed to carry 6 million Equivalent Single Axle Loadings, while future ESALs were estimated to be about 115 million over the next 20 years. High-strength concrete (800-psi flexural), dowels, short joint spacing of 15 feet, and reinforcing steel were used in the design. The reinforcing steel mats were added to enhance strength and provide for a margin of safety, even though design formulas do not account for this feature.” Diamond grinding was specified as the final finish.

APAC-Southeast’s Ballenger Paving Division received two Southeast Concrete Alliance Network awards for this project. SCAN is composed of state DOTs, the Federal Highway Administration, the Southeast Chapter of the American Concrete Pavement Association, concrete paving contractors, and equipment manufacturers and material suppliers. Awards are presented to all concrete paving and rehabilitation projects that meet the quality or innovation standards established by the SCAN Award Committee. Ballenger received the following awards for this project: the 2005 SCAN Quality Award in the Concrete Pavement Construction category; and the 2005 SCAN Innovation Award for advancing the knowledge and practice in concrete pavements.  


For more information, you can contact the American Concrete Pavement Association headquarters at 847-966-2272. ACPA maintains chapter offices throughout the country that stand ready to help with your concrete pavement questions. See also www.pavement.com.

Reprinted from Better Roads Magazine
August 2005

Click Here to return to article index

Copyright © 2005 James Informational Media, Inc.
All rights reserved.

Home/Site Map
 
Buyers Guide
Supplier/Equipment
Information
Products
Top Products & More!
Industry Links
Associations, Suppliers,
DOT's, Counties
Article Archive
A popular Starting Point
Articles and News
Event Calendar
Trade Shows/Exhibits
& Events
RoadFax Forms
On-Line inquiry form
Advertising
Rate Card,
Advertising Information
Circulation
Subscription Form
Editorial
Editorial Calendar,
Submission Guidelines
Search  Classifieds Contact Us