August 2006
Back to Article Index

  Get Copyright Permissions Click here for copyright permissions!
Copyright 2006 James Informational Media

 
Better Bridges

New Interchange Connects Two Arizona Freeways
A three-level overpass provides a complicated but traffic-easing solution at the I-10/I-19 interchange.

by Michael J. Hatchell

Building an interstate-to-interstate traffic interchange is a challenging endeavor under the best of circumstances. When the traffic interchange is on three levels and involves the demolition of nine old bridges and the construction of 10 new ones; building eight new ramps connecting the interchanges; reconstructing a city street, and creating a new extension to another city street while, at the same time, maintaining two lanes of interstate traffic in each direction, the task is nothing less than daunting. Yet, that is what was achieved in constructing The Crossing, a traffic interchange at Interstates 10 and 19 just south of the heart of downtown Tucson, Arizona.

Designed by URS Corporation for the Arizona Department of Transportation, the three-level I-10/I-19 traffic interchange involved the total reconstruction of the only existing traffic interchange in the Tucson area. The $54.3-million project creates a vastly improved interchange system. In addition to easing congestion in Tucson, The Crossing was intended to streamline traffic in what is called the Canamex Corridor, a tourism and trade route extending from Mexico to Canada.

According to Bill Dehn, consultant project manager for URS, “The new interchange is designed to handle anticipated increases in traffic through 2015. With some modifications, it will be able to accommodate increases for an even longer period.”

Safety issues

“Safety was a principal concern in the design of the project,” says Ana Olivares, ADOT project manager. “With 70,000 vehicles a day coming into the interchange, the tight turns on the ramps were particularly hazardous. The new ramps feature improved radiuses to allow drivers to access the freeway at higher speeds, while the split-diamond configurations solve bottlenecks that occurred with the old interchange design.”

Due to unsafe traffic merging in the area, the I-10 eastbound entrance ramp from 22nd Street and the I-10 westbound exit ramp to 22nd Street were moved and combined with the newly constructed entrance and exit ramps at 29th Street.  A third lane in both directions also eases congestion.

“The tight turns were acceptable when the old interchange was built more than 40 years ago,” Dehn says. “The sharp curves on both the old ramps were notorious for catching drivers by surprise and causing accidents. The new configuration will significantly reduce dangerous conditions.”

Innovative techniques

Keeping traffic moving while work proceeds is always a major consideration during road reconstruction. On most projects, the roadway is not opened until it is completed. However, sections of the traffic interchange had to be completed in order to move traffic onto it so the next phase could be built. The construction traffic control plans indicated that northbound I-19 be reduced to one lane while the inside lane was completed. When the lane reductions were put in place, the traffic backup in the area, especially during peak travel times, reached an unacceptable 2 miles in length. To ease the congestion, adding extra asphalt to the shoulder created an additional lane. The work had to be completed after the traffic was in restricted lanes, but the two lanes, though very narrow, helped to relieve the backup.  Later, when traffic needed to be switched again to complete northbound I-19, the extra lane was built prior to the switch, providing two lanes right from the start.

Another construction problem was the installation of a drainage pipe beneath I-10. Ordinarily, this would have involved an additional traffic switch and a jack-and-bore operation on a 66-inch section of pipe. An alternate method of placing the drainage pipe under and across the interstate was developed. The drainage pipe was installed as far as possible without interrupting interstate traffic, and the detour was built over the completed section of pipe. Next, the detour was swung a bit wider than had been planned and a little more pavement was added to it. That created enough room to keep interstate traffic moving while the open trench construction continued.

The demolition of nine bridges would ordinarily be a time-consuming, troublesome process conducted in two separate stages. First, the concrete would be crushed, then crews would arrive to cut and remove the remaining rebar.  However, an innovative technique was employed, using a state-of-the-art piece of equipment called the DemoPro. The DemoPro grabbed and crushed a section of concrete with its scissor-like jaws and continued to clamp down and cut all the way through the rebar. This method cut a full week from the demolition time of each bridge, a total saving of more than two months on the project schedule.

Environmental considerations

Extensive archeological evaluation during the design phase of the project led to a surprising discovery. Excavation unearthed a prehistoric settlement that had been occupied for more than 1,500 years. From approximately 400 B.C.E. to 1150 C.E., a section known as the Julian Wash area was part of a series of large Hohokam and pre-Hohokam villages that bordered the Santa Cruz River.  Nearly 100 prehistoric pit houses and household articles were exposed, along with a portion of an orphanage, St. Joseph’s Children’s Home. These areas were fenced off and left undisturbed during the construction process.

Another environmental measure involved the development of a Stormwater Pollution Prevention Plan, which addressed the problems of soil erosion, the loss of topsoil, and possible contamination of soil during construction activities.

“The Crossing is one of the largest highway improvement projects undertaken in southern Arizona during the past decade, in both size and importance,” says Olivares. “It was completed on time and under budget, and it has improved traffic flow and safety in one of the busiest traffic intersections in the state.”

Reprinted from Better Roads Magazine
August 2006

Click Here to return to article index

Copyright © 2006 James Informational Media, Inc.
All rights reserved.

Home/Site Map
 
Buyers Guide
Supplier/Equipment
Information
Products
Top Products & More!
Industry Links
Associations, Suppliers,
DOT's, Counties
Article Archive
A popular Starting Point
Articles and News
Event Calendar
Trade Shows/Exhibits
& Events
RoadFax Forms
On-Line inquiry form
Advertising
Rate Card,
Advertising Information
Circulation
Subscription Form
Editorial
Editorial Calendar,
Submission Guidelines
Search  Classifieds Contact Us