The newly opened White River Bridge uses four interlocking
114-ft. high pylon legs and two rows of massive cables that suspend the structure. The
design is the work of J. Muller International, a Chicago architecture firm that
specializes in complex bridges.
The 465-ft.-long structure is suspended from a center-locking quadripod pylon and two
radiating rows of cable stays. Engineers went to great lengths to guarantee the structural
stability of the unusual design.
The bridge is anchored by four permanent concrete-filled steel casings that are
socketed below the water and into bedrock. Milestone Contractors, the general contractor,
chose to pump concrete into the 6.5-ft.-diameter caissons, even though it was a challenge
due to the harsh mix and engineering design.
"The 90-ft. caissons were unusual in that they had to be filled with concrete
under water on a 64-degree slope," said Neil Comstock, senior construction manager
for Milestone Contractors. "This slope made it very difficult to maintain contact
with the mix and keep head pressures to a minimum."
To place the concrete, Milestone used a crane to lower a retractable 110-ft. pipe into
the caisson. Once lowered, Georges Concrete Pumping attached a 42X-Meter Putzmeister
boom pump hose to the pipe.

The pipe was positioned 7 ft. below the concrete level throughout each 80-cu. yd.
caisson pour. Tremendous line pressure had to be maintained to prevent water from coming
in contact with the Class A modified mix. Later, Georges also used the truck-mounted
pump to place concrete in each of the attached pylons.
Measuring 120-ft. long by 4.5 ft. in diameter, four hollow steel pylons extend up from
the caissons and connect above the bridge deck. By placing the pump hose in a hole located
60 ft. above the base of the pylons, Georges filled the bottom half of the pylon
with concrete, too. At the end of the pour, Georges placed a total of 470 cu. yd. of
concrete in the caissons and pylons.
The deck
At the top of the pylons is one of the most intricate components of the bridge, the
structural steel quadripod pylon head that anchors the 40 cable stays. Locked in the pylon
head, these cables suspend the entire bridge deck.
Georges used a pair of Putzmeister 42X-meter pumps to place 775 cu. yd. of
corrosion-inhibiting microsilica-modified concrete for the bridge deck. The pour took 14
hrs., while the deck was pre-loaded in front of the screed machine and testing was
performed at the end of the boom.
Post-tension cables in plastic tubing run throughout the deck Superplastizer was added
to the mix to make it free flowing and to help alleviate voids.
Post-tensioning
Seven days after the deck pour, the post-tension cables were tightened, giving the deck
a crowning effect and producing a longitudinal arch.
"We had some access difficulty due to the location of the pylon legs and head
section," says Comstock. "Air entrapment requirements were very tight, but
maintained throughout the pour at the pump discharge line."
Georges used a 5-in. to 4-in. reducer with two 4-in., 90-degree elbows clamped at
the end to help maintain air content.
"The placement of concrete for the caissons, pylon legs, and bridge deck was
discussed many times by the contractor, designer, supplier, and Indiana Department of
Transportation," said Comstock.
"Each operation had its own set of challenges such as access, mix design
requirements, and volume of cubic yards needed to maintain a good, consistent mix.
"We are very pleased with the equipment and Georges personnel,"
Comstock said. "It takes an entire team to make a difficult project a success."
The bridge opened to traffic in June.