February 2003
Back to Article Index

Better Bridges

Bridge Replaced in Sections — at Night

The Lions Gate Bridge truss and deck sections
 were replaced during 10-hour night closures.

by Michael Abrahams, Joseph Tse, and John Bryson

The bridge stayed open to traffic during the day. Such replacement for a major suspension bridge is believed to be unprecedented, especially where the bridge remained in service except during the 10-hour night closures.

The Lions Gate Bridge in Vancouver, British Columbia, Canada is a 1,518-meter-long bridge with a 473-meter-long suspended main span over the Burrard Inlet. Reconstruction of the 45-year-old, two-lane bridge is a part of an $80-million rehabilitation of the Lions Gate Crossing. The major structural components include seismic retrofit of both the north approach viaduct and the main span, widening of the approach span sidewalk, and replacement of the entire suspended span deck including hangers.

Deck replacement was to be done without interruption to bridge traffic during daytime hours; only nighttime closures lasting 10 hours were allowed for operations that interrupt traffic.

In order to accomplish these modifications, the owner selected a rather unique combination of the traditional design-bid-build with newer design-build methods. The many engineering challenges combined with the two methods of procurement make this project unique.

The seismic retrofit portion of this major project was probably the first of its size to be carried out as a design-build undertaking. The contractor, American Bridge-Surespan, a joint venture, retained an engineering firm, Klohn-Crippen, to conduct a seismic analysis and retrofit design and, as required by the contract, an independent consultant firm, Parsons Brinckerhoff, to conduct an independent analysis and design check.

The suspended span deck replacement was designed by N.D. Lea/Buckland & Taylor and was included in the contract documents. However, other than a limited erection analysis, which considered only dead and live loads, it was left to the contractor to develop the deck replacement methodology and erection equipment.

The erection analysis was conducted by one consultant, the Parsons Transportation Group Major Bridge Division (PTG-Steinman), and was checked with an independent analysis by a second consultant, Parsons Brinckerhoff. All erection equipment required an independent check. In this case the erection equipment was designed by American Bridge-Surespan engineering staff with an independent design check by PB.

Seismic retrofit

The structure was retrofitted to a level of performance such that it would remain open to traffic following a 475-year design level event.

The approaches are tall with piers up to 160 feet in height. They are made up of steel plate girders (orthotropic deck) supported on slender steel piers that use laced members for bracing elements. The piers are supported by spread footing foundations.

There were three primary elements to the retrofit:

1. Build-up the existing H-bents so they can anchor the structure longitudinally.

2. Allow piers to rock transversely.

3. Add piled foundations in areas where liquefaction potential is high.

There were two types of foundation retrofits. The first was pile-supported reinforced concrete grade beams that tied the existing spread footings together. This retrofit detail was used in zones of potential liquefaction. The second type was comprised of reinforced concrete grade beams without pile supports. The purpose of this grade beam is mainly to tie the foundations together. These foundation designs considered the effects of rocking, and some ductility was allowed in foundation grade beams.

The piers were retrofitted to provide additional bracing for the chevron bracing system to prevent buckling. Push-over analysis was used to determine the sequence of events between yielding and failure, and to gain a more complete understanding of the system behavior.

To capture the non-linear behavior of the structure rocking, an ADINA model was developed to account for effects such as p-delta on the steel piers and pounding as the rocking piers landed. The design limited the pounding effects by incorporating a TADAS device at the base of the piers. The non-linear behavior of this element was also included in the design evaluation model.

The TADAS device was installed at the base of the tower legs to resist and dampen rocking. This device uses a pinned/fixed plate to develop resistance. The narrow end is pinned in the slotted keeper and the wide end is bolted to the column leg. This results in predictable, ductile behavior for the TADAS device. The device is also easy to fabricate and easy to replace.

Seismic retrofitting was also required for the superstructure. Existing superstructure cross-frames were not adequate to carry inertial loads into the piers. A combination of local and global models was used to determine the loads and load paths in the superstructure. Additional cross-frame members were added at the pier locations in order to complete the load paths needed to carry inertia loads from the superstructure into the substructure.

Deck replacement

The new deck carries three 3.6-meter traffic lanes, and two 2.7-meter sidewalks. The deck is of welded orthotropic steel-plate construction with stiffening trusses utilizing welded rectangular hollow sections. The new stiffening trusses are located below the deck and are 2.08-meters deep. The number and location of the hangers that support the new deck remain the same as the original deck. The new deck is 4.5% lighter than the existing deck in the main span, and 3.1% heavier on the side spans; a significant design consideration for the erection engineering.

The condition of the bridge prior to construction was poor for several reasons. Traffic loads are substantially greater than originally intended. Then, load changes and geometric changes resulted in a sag at mid span of over 1 meter. Corrosion of the floor system had further reduced the capacity of many of the stringers and floorbeams. The bridge required ever-increasing load restrictions prior to reconstruction.

The challenge in this project was the very limited additional capacity of the bridge to accommodate erection loads and deformations. The original design of the bridge economized on every element to the maximum extent possible, and at the time of its design, was only for two lanes of traffic with no sidewalk. There was no consideration of seismic forces, nor were analytical methods very accurate. Over time, the effects of section loss, cable and suspender stretch, and cable slip further reduced the bridge’s capacities.

The contract documents listed changes in the bridge geometry between the original design and field survey data collected through 1998. The contractor was required to conduct an independent survey to verify the listed changes and provide updates as necessary. With all information gathered, interpreted, and resolved, our computer models were adjusted to account for these primary geometric corrections, namely, the suspension cables had sagged around 1,120 mm at the mid-span, and the North and South Towers had deflected 160 and 90 mm, respectively, towards mid-span.

The difference in the vertical alignment of the existing deck and the new deck — the existing main span deck had an abrupt 8% grade change at the center (believed to be associated with the need to reduce construction costs). This break in grade was to be taken out with the installation of the new deck. The computer models used by both PTG-Steinman and PB were developed to account for this difference by systematic tracking of hanger fabrication length and intermediate hanger adjustments for proper alignment across the continuity link.

The existing structure had little reserve capacity for construction loading and geometric effects. As a result, fine-tuning of the hangers, especially around the work front, was necessary in each stage to keep hanger loads within allowable limits. Likewise, the existing truss diagonal members required reinforcement to avoid being overstressed. A hydraulic spring was also necessary to prevent overstressing the chords of the existing truss in case of high winds when replacing the main span sections. This required 3-D computer models be developed with multi-linear springs to simulate the hydraulic system. The flexibility introduced by the continuity link in turn required measures to mitigate overstressing of the chord members due to significant inclinations during construction in the existing and new hangers.

Replacement

After evaluating alternatives, the contractor and PTG-Steinman settled on a scheme that involved replacing the existing deck in sections of 19.66 meters in length for the north side span and the main span. The 19.66-meter sections were raised and lowered to, and from, the ground or barges in the water. At the south side span, the steep slope and environmentally sensitive nature of the park grounds below required the deck be removed from above; sections of 9.83-meter length were removed/delivered through the south end of the bridge.

The contractor custom designed and fabricated equipment. Essentially a steel lifting frame, the jacking traveler advanced with the work front by rolling along the deck on Hillman Rollers. In its operating mode, the frame was attached to the hangers with the supporting legs retracted. Strand jacks that were mounted on top of the frame were engaged to support the weight of either the existing deck or the new deck during the various stages/steps of the replacement operation. There were two versions of the traveler — one for the north side span and main span, and a shorter version that was used at the south side span.

When the bridge was reopened to traffic at the end of each replacement stage, a continuity link was needed at the erection front to join the existing and new deck sections together. The continuity link had two steel components; each attached to one of the two bottom chords of the existing truss. Each steel component housed an extendable/retractable key that extended to engage its counterpart (called the link nose) attached to the new deck. The key maintained vertical alignment across the work front providing shear continuity and thus ensuring rideability between the new and the existing deck sections.

The contractor provided a temporary deck section that could be deployed rapidly to fill a gap in the deck in the event of unforeseen circumstances such as a failure of the erection equipment or misfabrication of the new deck section. The temporary deck was designed to support three lanes of reduced traffic load and full design wind load.

The existing hangers were replaced by new and longer hangers attached at the roadway level of the new deck. This replacement operation trailed behind the deck replacement and removed itself from the critical path. Before the new hangers could be installed, hanger extensions were required to provide a link between the connections at the new deck and the shorter existing hangers. The hanger extensions were detailed with adjustment capabilities so that adjusting the hangers dispersed localized overstresses in the hanger and truss members near the work front.

The bridge under construction was much more flexible than either the existing structure, before reconstruction began, or the new structure, when completed. As a result of detailed analyses, a significant number of connections were found to require special details to accommodate the rotations of the suspenders associated with the increased flexibility.

The bridge was vulnerable to high winds when the deck section was discontinuous. The contractor installed fairings at the main span to improve aerodynamic stability of the structure during reconstruction. It was also established that the bridge could withstand a wind speed of 12 meters/second in its open condition. Therefore, night closures for deck replacement were ordered only when the forecast wind gust speed was less that 10 meters/second.

Typical replacement steps were:

1. Initial condition. The jacking traveler is rolled into position for replacing a given deck section. The continuity link engages the new deck to the existing deck. Traffic is running.

2. The jacking traveler is attached to the hangers and its weight is transferred to the hangers as the supporting legs are retracted.

3. Traffic is stopped. The continuity link is disengaged and rolled southward, clearing the target deck section for replacement.

4. The strand jacks take up most of the weight of the target deck section. The existing truss hanger socket plates are removed. The existing truss top chord, bottom chord, and diagonal are cut. The link nose is removed from the target deck section and relocated to the end of the remaining existing truss.

5. The section of existing truss is lowered to the ground or barge. The continuity link nose is removed from the bridge and attached to the next new deck section.

6. The next new deck section is hoisted into place and incorporated. Temporary hanger extensions are installed and the strand jacks released.

7. The continuity link is moved northward as required to engage the link nose. The continuity link traffic plates are installed. The new deck splice traffic ramp is moved ahead. The hangers are adjusted to predetermined forces/extensions that will accommodate all the loading conditions expected until the next stage.

8. The bridge is reopened to traffic. The jacking traveler rail is moved ahead and the jacking traveler legs are extended to engage the Hillman Rollers. The jacking traveler is winched forward on the Hillman Rollers. Various pieces of construction equipment are relocated ahead for the next stage.

The south side span sections were replaced in 9.83-meter segments, which were half the length of those for the north side and main spans. Removal of the existing truss involved cutting the section free, lifting and rotating it 90 degrees, and lowering the section onto the back of a specially designed transporter that was waiting on the deck at the work front. To accommodate the heavier construction loading for these operations, both existing and new hangers were adjusted at each stage to more favorably re-distribute the loads near the work front. (On the north and main spans, only the new hangers were adjusted.)

The Lions Gate Bridge is believed to be the first major suspension bridge that was seismically retrofitted under a design/build format. It is also believed to be the first major suspension bridge that had its deck completely replaced while maintaining traffic.

In the case of the deck replacement, wind issues combined with the need to maintain traffic is perhaps more complex than the construction of a new suspension bridge. Compounding the wind issue is the fact that the existing bridge lacks reserve capacities for construction loading and deformations. Moreover, solutions to these engineering challenges were provided under significant time constraints. The construction engineers solved the engineering challenges by using sophisticated computer software, old-fashioned hard work, and engineering judgment. The bridge behaved close to the construction engineering teams’ prediction.


Michael Abrahams, P.E., Joseph Tse, P.E., and John Bryson, P.E. represent Parsons Brinckerhoff Quade & Douglas, Inc., New York, New York.

Reprinted from Better Roads Magazine
February 2003

 

Click Here to return to article index

Copyright © 2003 James Informational Media, Inc.
All rights reserved.

Home/Site Map
 
Buyers Guide
Supplier/Equipment
Information
Products
Top Products & More!
Industry Links
Associations, Suppliers,
DOT's, Counties
Article Archive
A popular Starting Point
Articles and News
Event Calendar
Trade Shows/Exhibits
& Events
RoadFax Forms
On-Line inquiry form
Advertising
Rate Card,
Advertising Information
Circulation
Subscription Form
Editorial
Editorial Calendar,
Submission Guidelines
Search  Classifieds Contact Us