February 2004
Back to Article Index

Better Bridges

Missouri Cable-Stayed Bridge Opens

After three years, the new Cape Girardeau Bridge now moves traffic across the mighty Mississippi.

by April Goodwin

The new cable-stayed structure stretches for the length of 13 football fields over the famous waterway

Two H-shaped towers, constructed of reinforced concrete, hold up 64 support cables each and extend 330 feet above the water. The cable strands are concealed by a white, high-density, polyethylene pipe and plastic sheath. Altogether, the strands that make up the diagonal cables could span for 171 miles, according to the Missouri Department of Transportation.

Construction of the Cape Girardeau Bridge, also called the Emerson Memorial Bridge, is estimated at $100 million; 80% of the funding comes from the federal government. The other 20% of the cost is split between Missouri and Illinois.

Getting started

The design of the bridge began in 1996 and major construction started in June 2000, when the MoDOT awarded a contract to Evansville, Indiana’s Traylor Brothers Inc., one the foremost bridge contractors in the world. Traylor Brothers has completed more than 130 major bridge projects, including some of the largest and most complex bridge projects in the world.

The MoDOT contracted Traylor Brothers to:

  • Complete Pier 2.
  • Construct Piers 3 and 4.
  • Install 128 stay cables.
  • Construct the bridge deck on the main bridge and the Illinois approach bridge.
  • Install 140 decorative lights.

Substructure work included two dredged caissons and two 364-foot-tall main pylons. Superstructure work included installation of the stay cables, 8 million pounds of structural steel, and an 11-inch-thick precast concrete deck with 3-inch-thick poured-in-place micro silica fume overlay concrete.

The suspended four-lane highway is 96-feet wide, and rises 60 feet above the Mississippi. The deck is composed of steel plate girders and floor beams and pre-stressed concrete slabs. A concrete barrier is located in the center of the bridge, and two concrete railings are placed along the edges of the deck.

The overall weight of the bridge is 266-million pounds — equal to the weight of 304 jet airplanes. Crews are using an estimated 13-million pounds of reinforcing steel and 243,688,500 pounds of concrete to build the bridge.

Annual status reports

By the summer of 2001, Traylor Brothers had finished the dredged caisson for the Illinois-side pylon despite some nasty winter weather in late 2000 and early 2001, and one minor challenge: driving the caisson the last 10 feet.

In order to force the caisson to sink the final distance, a blasting subcontractor was hired to set off explosive charges that shook it down. A total of 58 rounds were needed to complete the job. After the caisson was landed and the bottom cleaning was finished, it was a mad rush against a rapidly rising river to get the tremie seal concrete poured.

On Friday, June 1, 2001, the crew received a forecast that predicted the river to rise above flood stage early the next week. Traylor Brothers decided to begin the tremie pour the next morning and pour through the weekend in an effort to beat the flood. Two crews traded 12-hour shifts to complete the 4,700-cubic-yard pour by early Monday morning. The MoDOT reported it to be its largest concrete pour on record. Shortly after the record-breaking pour, the river flooded. As it turned out, if Traylor Brothers had not pushed through the alternating 12-hour shifts, the crew would’ve been delayed by about eight weeks.

By the summer of 2002, the 350-foot Missouri pylon was complete and the crew was focusing on the Illinois pylon, which was well along. Work was also progressing on the Illinois back pier. Several pours were finished, including a 1,900-cubic-yard distribution block concrete pour and six-stem pours, ranging from 750 cubic yards to 1,200 cubic yards. Eleven of the 30 tower leg pours for the Illinois pylon, averaging 80 cubic yards each, were done, and the follower and sand island cofferdams for that pier had been removed.

By the spring of 2003, construction of the 356-foot main pylon in the center of the river was complete. Stem construction for the Illinois back pier was also complete and 16 of the 64 stay cables for the Illinois pylon were installed. Rebar installation and deck concrete placement on the Illinois approach bridge was in progress and superstructure erection of the Missouri pylon was well underway. All stay cables were in place by August. Owens said superstructure finish work, overlay, barrier walls, and cable grouting should be complete by the end of the year.

Rental equipment

Rental Equipment from RSC, one of three brands belonging to Rental Service Corporation, Scottsdale, Arizona, North America’s second largest equipment rental company, played a vital role during construction of the bridge. Traylor Brothers has rented a variety of equipment from the local RSC stores since December 2000 — everything from mini excavators, skid-steer loaders, and air compressors to variable-reach forklifts, pressure washers, brush chippers, and diaphragm pumps.

The contractor prefers to own its own equipment but occasionally needs to rent equipment when there isn’t a company-owned machine available — or when it is more cost effective to rent equipment than to transport an owned piece to the jobsite. Project Manager Larry Owens says Traylor Brothers also rents if a piece of equipment is only needed for short-term use, or if a unique size or capability is required.

In the case of the Cape Girardeau Bridge, Traylor Brothers rented several items from RSC, including several 120-foot boom lifts, a ride-on broom, and half a dozen light towers.

The crew used the boom lifts for access when performing miscellaneous tasks like concrete patching, form stripping, steel bolt ups, and so on. The broom was used to quickly and efficiently clean up the bridge deck. The light towers were used for night work.

Time to open

Cape Girardeau has evolved over the past 200 years from the tiny French trading post it once was. The Bill Emerson Memorial Bridge replaces a bridge built in 1927 and is expected to handle the increased traffic flow in the area.

An estimated 14,000 vehicles cross the bridge daily. By the year 2015, the Missouri Department of Transportation estimates about 26,000 vehicles will cross the bridge each day.

In mid-August, cranes on barges lowered two 3,700-pound, 6-foot-long steel girders in place to close the gap.

By September, all of the deck panels were in place, the cables adjusted, and a 3-inch concrete surface poured across the length of the span. Then, concrete barrier walls and electrical work were completed and decorative lighting added. In addition, grout was pumped between the polyethylene casing and plastic sheathing that covers the steel cables.

After the last of the pre-cast deck panels was erected, a 3-inch driving surface to the cable-stay portion of the bridge was installed. Traylor Brothers used special concrete containing silica fume, a byproduct of silicon metal. Concrete containing silica fume is highly impermeable and has an estimated life of 50 years. 


April Goodwin is a technical writer in Des Moines, Iowa.

Reprinted from Better Roads Magazine
February 2004

 

Click Here to return to article index

Copyright © 2004 James Informational Media, Inc.
All rights reserved.

Home/Site Map
 
Buyers Guide
Supplier/Equipment
Information
Products
Top Products & More!
Industry Links
Associations, Suppliers,
DOT's, Counties
Article Archive
A popular Starting Point
Articles and News
Event Calendar
Trade Shows/Exhibits
& Events
RoadFax Forms
On-Line inquiry form
Advertising
Rate Card,
Advertising Information
Circulation
Subscription Form
Editorial
Editorial Calendar,
Submission Guidelines
Search  Classifieds Contact Us