February 2005
Back to Article Index

Better Bridges

Bridge Jacking Goes to Greater Heights

Two bridges in the Salem, Oregon area were recently elevated using the process.

by

The slow and methodical procedure uses hydraulic jacks to raise the bridges inch by inch to the preferred height.

The Battle Creek structure over Interstate 5 south of Salem was raised 30 inches to a height of 17 feet, 5 inches. The Lafayette Avenue Bridge that crosses Highway 18 east of town was elevated 24 inches to a height of 16 feet, 10 inches. The completed projects will provide appropriate clearance for commercial vehicles using both highways.

“We don’t see this type of operation very often in this region,” says Oregon Department of Transportation Assistant Project Manager Ray Bryant. “It is done around the country all the time, so the process is tried and true.”

How it works

The process begins with attaching a steel brace around the bridge columns for lateral support.

A core drill is used to remove concrete from the center of the columns to provide room for the jacking box.

The box is installed using grout on the top and bottom to get even bearing pressure for the jacking process. The jacks are placed in the box and activated to the theoretical dead load for each column. This will relieve the compressive load off the portions of concrete that remain on two sides of the column.

Workers begin shim insertions. 

Photo shows jacking progress. 

Coordination of bent raising is critical.

Once all the jacks are in and activated, the remainder of the concrete is removed so all that remains are four vertical pieces of rebar.

Before the jacking begins the rebar is cut with a torch and the hydraulic jacks start elevating the bridge.

The bridge is raised and steel plates called shims, which range from a 0.25 to 2 inches, are placed in the column until the maximum height of the jack is reached.

The hydraulic pressure is then released until the bridge rests on the shims. The 2-inch shims are welded at 6-inch intervals.

When the desired height is reached mechanical splices are used to replace the missing rebar.

Concrete is poured back into the columns and allowed to cure for 14 days.

The road approaches on both sides of the bridge are built up to match the new height of the bridge.

On site

The Lafayette Bridge has four bents; each bent has four columns for a total of 16 columns plus two end bents. Twenty-four jacks were used to elevate the entire structure.

The Battle Creek structure has three bents with two columns per bent and two end bents.

“The columns are probably the best place for dealing with all the forces of the bridge,” says Bryant. “Because the only thing you have there is straight compression and no other forces to deal with.”

The Battle Creek and Lafayette bridges were raised because of damage caused when over height loads hit the structures and chipped away concrete from the bottom portion of the bridge deck and also severed reinforcing steel on the exterior girders.

This past spring, one lane of Interstate 5 was closed for a short period after the Battle Creek Bridge was struck by a semi truck and chunks of concrete fell on several vehicles. No one was seriously hurt.

“Usually what happened is when a low boy with a track hoe travels under the bridge, and because of the hydraulic bleed off, the knuckle raises the track hoe arm enough to strike the bottom of the bridge,” said Bryant.

The Oregon Department of Transportation placed load restrictions on the bridge because of damage from heavy loads and cracks due to age.

The Battle Creek work was part of a bigger project that cost $4.2 million and consisted of paving this section of I-5, rebuilding 12 bridge approaches, abandoning the Boone Road Bridge, replacing old median guardrail with new tall concrete barrier, and replacing old bridge guardrail with new. In addition, shear cracks, some up to 0.025 inch, on the Battle Creek Bridge were filled with epoxy.

The Lafayette Bridge project cost $633,000.

Raising the Lafayette Bridge, and the Battle Creek Bridge with a dead load per bent of approximately 300 tons or 75 tons per column, requires a heavy-duty jacking system. ODOT standards require the system to be capable of supporting one and a half times the dead load.

There are carbureted hydraulic systems located at each one of the bents so all four columns at one bent are under the same hydraulic system.

During the jacking of the bridge each bent is raised independently and timed accordingly so all bents are elevated at about the same time. The workers communicate with radios during this procedure or by whiteboards as was the case at Battle Creek on I-5 because of the noise.

“So that is why you really only go up a quarter inch at a time,” said Bryant. “You don’t want one bent going up faster than the other because that could cause some stresses in the bridge you don’t want.”


Dan E. Knoll represents Region 2 of the Oregon Department of Transportation.

Reprinted from Better Roads Magazine
February 2005

Click Here to return to article index

Copyright © 2005 James Informational Media, Inc.
All rights reserved.

Home/Site Map
 
Buyers Guide
Supplier/Equipment
Information
Products
Top Products & More!
Industry Links
Associations, Suppliers,
DOT's, Counties
Article Archive
A popular Starting Point
Articles and News
Event Calendar
Trade Shows/Exhibits
& Events
RoadFax Forms
On-Line inquiry form
Advertising
Rate Card,
Advertising Information
Circulation
Subscription Form
Editorial
Editorial Calendar,
Submission Guidelines
Search  Classifieds Contact Us