July 2003
Back to Article Index

ASPHALT IN-PLACE RECYCLING

CALIFORNIA PUTS 
FOAMED ASPHALT TO THE TEST

Conventional reconstruction of the California Delta’s rural roads
 is cost prohibitive, so Caltrans is testing foamed asphalt as a solution.

by Tom Kuennen, Contributing Editor

In the famous Delta region of California’s San Joaquin Valley, where the California Delta sprawls across 738,000 acres of prime agricultural land south of the state capital, farm roads are built on an excavated alluvium that just won’t stay in place.

The roads are subject to baking hot weather in summer and drenching cold Pacific rain storms in winter, and agricultural trucks that often are well overloaded. Road driving surfaces heave, shift, and collapse.

In maintaining these roads, the owning agency, the California Department of Transportation, has a perplexing problem: The cost of conventional reconstruction of these roads — months-long closure, excavation, trucks out with old pavement and base, trucks in with new base and pavement materials, and a parade of construction equipment — made reconstruction prohibitively expensive, considering their remote location and the few vehicles per day they served.

But Caltrans may have found the answer with in-place base recycling using foamed or expanded asphalt. Contractor Western Stabilization applied this process as a state pilot project late last year. Western Stabilization performed the job with the powerful Wirtgen WR 3000.

With its 10-foot-wide drum, the WR 3000 is big brother to the more common WR 2500 S with an 8-foot-wide drum. However, the equipment platform is the same, and the only difference between the two models is the width of the drum and the mechanics and hydraulics that serve it.

Agricultural lowlands

The California Delta is a network of a thousand miles of rivers, tributaries, and channels located south of Sacramento. Much of the land is composed of large islands that sit below sea level, protected by levees, isolated by streams and canals fed by five major rivers, including the Sacramento and the San Joaquin rivers.

Water is such a part of the delta that folks refer to the roads and highways as “asphalt sloughs”.

One such “asphalt slough” is California 220, a blacktop road which last year was nearing complete failure. In late 2002, a 3.1-mile length of the road in Solano County became a testing ground for foamed asphalt.

The road suffered from longitudinal cracks, with cross-slope anywhere from 3 to 5%. Existing asphalt had been placed in depths from 6 to 18 inches. And while traffic is very light, heavy agricultural loads do their damage. Corings indicated not much base below the pavement.

The road was being stabilized 6-inches deep, except where roadway “whoop-dee-doos” — base failure-related “roller-coaster” waves in the pavement — were present. Those were being stabilized to a depth of 10 inches, which would allow more material for a motor grader operator to smooth out voids and take out humps.

Cold foaming prolongs life

“If we had done conventional reconstruction on this road, and dig-outs, we’d end up with a very, very limited life,” said Caltrans North Region materials engineer Joseph F. Peterson, P.E. “By cold foaming to a depth of 6 inches, we believe that we’re going to add 10 years of life.”

“Foamed” or “expanded” asphalt is a road base recycling process in which pulverized pavement is mixed with an asphalt froth to create a stabilized road base. The foamed asphalt is formed by carefully injecting a predetermined amount of cold water into hot penetration-grade asphalt in the mixing chamber of a pavement remixing unit.

There, air bubbles in the expanded liquid asphalt froth act as the carriers of liquid asphalt to fines in a reclaimed asphalt pavement aggregate mix. While expanded asphalt doesn’t completely coat all aggregate surfaces, it does form a mortar or glue which bonds the particles together.

In less than 15 seconds, the froth subsides and the dispersion of asphalt is achieved, eliminating time waiting for the “break” required when expensive asphalt emulsions are used. The technology also sidesteps use of costly cutback solvents. The liquid asphalt cement is pure, with nothing added to it to change its properties. That makes it more economical to use than emulsions, which are a processed oil.

Caltrans’ foamed asphalt mix design called for 2.25% liquid asphalt, and 1% cement. The cement was required because of the lack of base material and minus 200 material, as investigations indicated. Also, water for compaction was being added to the mix at a rate of 1.5 to 2.5%, depending on weather conditions. The water also was serving to activate the cement.

Road treated in two passes

The road was being treated in two passes. The initial foamed surface was compacted with a sheepsfoot roller, then rough-graded, compacted with a smooth roller, and fine graded, all without stakes required. A rubberized chip seal was to be placed as a driving surface.

As always with foamed asphalt stabilization, a mix design using actual materials from the job site must be developed prior to construction. The tool used for this job was a Wirtgen portable WLB 10 foamed asphalt lab. Western Stabilization owns a WLB 10, and so does Caltrans.

“Right now we have a lot of roads that are highly distressed and, given our high traffic loads, we need a methodology to rebuild our roads quickly and with minimum impact,” said Caltrans’ Peterson. “Cold foam seems to have the ability to build a road from the bottom-up, in a timely manner, and has very little impact to traffic.”

And that was borne out on California 220. “This cold-foamed asphalt process will take us four working days to rebuild from bottom-up at a depth of 6 inches,” Peterson said. “We’ll put a chip seal on top and that will take another two days, so in effect we’ve rebuilt the roadway in six days. If we were to do this conventionally, we’d be out here for 30 to 60 days.”

Still, the route 220 job is a pilot project as Caltrans studies the efficacy of foamed asphalt in different climates.

“We’re evaluating the cold foam under different conditions,” Peterson said in late 2002. “We’ve used it in a valley environment in which there are wild temperature swings, and we just completed 20 lane miles in snow country near Truckee, so we can see how it behaves under freeze-thaw conditions. And now we’re trying it here in the delta as a maintenance strategy, so we can see if we can rebuild the roadways very economically and quickly.”

Contractor spreading word

The California 220 project also served to introduce local government agency personnel — and Caltrans engineers from other parts of the state — to the foamed asphalt process.

“We’ve had visitors from different cities and counties, and from the University of California-Berkeley,” said Paul Jones, foamed asphalt business development manager, Western Stabilization. “I’m spreading the word on foamed asphalt and bringing individuals to view the job on-site, rather than hear about it in the office. It can open a lot of doors for us.”

“We’re able to work without road closures, and provide a road that will meet all criteria for less money, less time and with less environmental impact than conventional construction,” Jones said. “That’s because we’re not trucking aggregate in and out, but using the existing material in-place.”

While Western pursues the big fish, it hasn’t forgotten the smaller local governments, which form a major part of its foamed asphalt stabilization work, said Dick Stuart, general manager.

“Smaller jurisdictions may be able to put a project together within its maintenance budget, as opposed to new construction,” he said. “They also tend to be squeezed the hardest financially, so they’re looking for the most economic way to improve their roads, and foamed asphalt stabilization has proven to be a very economical solution.”

More information about contractor Western Stabilization is available at www.wstabilization.com. More information about foamed asphalt is available at www.wirtgenamerica.com.

Adapted with permission from Wirtgen Technology, Spring, 2003.

Reprinted from Better Roads Magazine
July 2003

 

Click Here to return to article index

Copyright © 2003 James Informational Media, Inc.
All rights reserved.

Home/Site Map
 
Buyers Guide
Supplier/Equipment
Information
Products
Top Products & More!
Industry Links
Associations, Suppliers,
DOT's, Counties
Article Archive
A popular Starting Point
Articles and News
Event Calendar
Trade Shows/Exhibits
& Events
RoadFax Forms
On-Line inquiry form
Advertising
Rate Card,
Advertising Information
Circulation
Subscription Form
Editorial
Editorial Calendar,
Submission Guidelines
Search  Classifieds Contact Us