|
In 2005, the FHWA Central Federal Lands in Denver funded a pavement
rehabilitation project in the park. The 5 miles of the Scenic Drive,
and about 1 mile of roadway from the south park entrance to the
Scenic Drive, were to be rehabilitated.
The general contractor was Interstate Rock Products of Hurricane,
Utah, and the reclamation/ stabilization portion of the work was
subcontracted to Son-Haul of Fort Morgan, Colorado. The contract
called for full-depth
reclamation of the asphalt pavement and base soils to a depth of 8
inches. The reclaimed material was stabilized with foamed asphalt
and Portland cement. After the stabilized base had cured, a 2.5-inch
hot-mix asphalt overlay was placed. A single chip seal was to be
applied in early 2006 so the roads will have the red color desired
by the NPS.
Scott Wolfert, P.E., project manager of the FHWA’s Central Federal
Lands, and Robert Quadland of Parsons Brinckerhoff were the
inspectors for the FHWA. All quality control testing was done by
Travis Howlett of Earth Engineering Consultants of Fort Collins,
Colorado. The initial mix design for the foamed asphalt
stabilization process was also done be EEC. Sonny Weimer, president
of Son-Haul, was the contractor’s QC supervisor.
What is foamed asphalt?
Foamed or expanded asphalt (or bitumen) is a relatively new road
base recycling process in the United States.
With foamed asphalt, a stabilized road base is created by carefully
injecting a predetermined amount of cold water into hot Performance
Graded (penetration-grade) asphalt in a pavement remixing unit,
approximately 2 to 3% percent water by weight of
asphalt.
Hot liquid asphalt rapidly expands into millions of bubbles (foam)
when it comes into contact with cold water, similar to the
spattering which takes place when drops of water stray into hot
cooking oil on a stove top. When injected into the hot liquid
asphalt, the water evaporates abruptly, thus causing explosive
foaming of the asphalt in the saturated steam.
The water is the carrier of the atomized asphalt, and within a few
seconds, the asphalt can thus be expanded to 15 to 30 times its
original volume. Precisely added water allows control of the rate
and amount of asphalt foaming or expansion. The expanded asphalt has
a lower viscosity and a resulting high surface area available for
bonding with aggregate fines.
The intensity and effectiveness of the foaming process can be
further improved by control of pressure and temperature, which is
possible when in-place foamed asphalt road stabilization is
accomplished in a remixing unit designed for that purpose.
The foamed asphalt is immediately mixed with the reclaimed asphalt
pavement and the base
material.
While expanded asphalt doesn’t completely coat all aggregate
surfaces, it forms a mortar or glue which bonds the particles
together. The expanded asphalt has an affinity for finer particles,
those of 75 microns or less. This effective coating of finer
particles increases the available surface area of the expanded
asphalt for bonding with the coarser particles of material and spot
welds the material matrix together.
Typically, the recycling or mixing machine is coupled with an
asphalt supply tanker which is propelled by the recycler and a water
cart which is pulled by the
recycler.
When hot (350 degrees F) liquid asphalt cement is injected with a
small amount of water, the volume of most types of liquid asphalt
expands greatly as it forms black foam. Two foam properties are
critical to successful road base stabilization, the expansion ratio
and the foam’s half-life.
The expansion ratio is the maximum volume of foam relative to the
original asphalt volume and is an indicator of how well the foam
will disperse and coat the RAP and soil particles in the reclamation
process. The half-life is the amount of time it takes for the foam
to collapse to 50% of its maximum expanded volume and is an
indicator of the foam’s stability. As the asphalt temperature or the
amount of injected water increase, the expansion ratio increases,
but the half-life decreases. Typically, an expansion ratio of 15
times and a half-life of 12 seconds are best for the base
stabilization process.
However, each foamed asphalt mix design is different and must be
undertaken based on materials that will be encountered on-site.
Based on lab tests of material extracted from the existing roadway,
the initial mix design called for 3 +/- 0.3% foamed asphalt plus 1%
Portland cement, and compaction of at least 97% modified Proctor
maximum dry density.
Bus traffic drives structural design
The 20-year pavement structural design was relatively high for a
Federal Lands project (800,000 to 1,000,000 ESALs). About 70% of
this loading was projected to come from the intensive shuttle bus
traffic. Design engineers limited the maximum grade rise to 2.5
inches to meet minimum geometric and safety standards. To meet these
criteria, an 8-inch foamed asphalt FDR followed by a 2.5-inch HMA
overlay was specified. This design is projected to accommodate about
600,000 ESALs or 14 to 15 years of service life.
On this project, a prototype SH-1000 cement/asphalt/water buggy —
designed by Sonny Weimer, president of Son-Haul Inc., and built in
their Fort Morgan, Colorado, facility — was used with a Wirtgen WR
2500 S reclaimer. Individual chambers of the buggy hold 6,000
gallons of asphalt, 25 tons of cement, and 1,500 gallons of water. A
burner unit in the
SH-1000 kept the asphalt at the 320-degree F minimum, the asphalt
temperature at which foam expansion was maximized.
The Wirtgen WR 2500 S reclaimer pushed the buggy as it fed precise
proportions of asphalt and water into the cutting chamber and spread
cement dust-free on the pavement in front of the
reclaimer.
Initial compaction was provided right behind the WR 2500 S by
several passes of a Hamm Model 3412 vibratory padfoot roller. A
motor grader then bladed the recycled material to produce a smooth
riding surface with the proper cross-slope. The specified 97%
density was achieved by additional rolling with a steel vibratory
roller. The recycled base was then lightly watered and rolled with a
rubber-tire roller. The action of the rubber tires on the wet foam
stabilized base created a slush that brought fines to the surface.
These fines made the surface smooth, tight, and ready for traffic.
While traffic can ride on the foam-recycled base once compaction is
complete, a surface seal is (usually) eventually required. On this
project, a 2.5-inch HMA pavement added structure and sealed the
stabilized base. A single chip seal with a local red aggregate was
to be placed in 2006 to provide a final aesthetic touch to assure
that the road fits into its surroundings and will “lie lightly on
the land”.
Ed Kearney is director of engineering,
Wirtgen America Inc. |