May 2003
Back to Article Index

Better Bridges

Nebraska Opens Flooded
 I-80 Bridge Approaches in 5 Days

by Mary Jo Hall, Nebraska Department of Roads.

A deluge in western Nebraska caused the closure of a 7-mile stretch of Interstate 80, America’s busiest highway, while two bridge approaches that washed out in the weekend flood were repaired.

After Nebraska Department of Roads Director John Craig declared that fixing I-80 was top priority, a massive effort was launched to mobilize forces and begin repairing the damaged bridge approaches near Ogallala. Fifty workers from 10 different contracting companies and 30 state DOR employees worked around the clock to restore the cross-country freeway. Before Saturday morning’s flood, an estimated 20,000 vehicles per day traveled that stretch of interstate.

As soon as the flooding receded the following Monday, engineers determined that the bridges were structurally sound and only the approaches needed rebuilding. Because Nebraska Governor Mike Johanns quickly declared the area a disaster, the DOR was allowed to forgo the usual bidding process to find a contractor. Paulsen Construction Company in Cozad, Nebraska was selected as the primary contractor, with 10 other contractors involved in the cooperative effort. With an estimated completion date of the following Monday, and an estimated repair cost of less than $1 million, the work began.

Equipment was mobilized from across the state and lights were erected so work could continue through the night hours. Six massive floodlight units were brought in.

On Tuesday, heavy equipment was used to break up the massive slabs of concrete that dropped into the Western Canal when the ground beneath it was carried away. On Tuesday and Wednesday, workers hauled in the tons of dirt needed to fill in the washed-out approaches. More than 20,000 cubic yards of fill were required for the job, and more than 25 trucks were hauling at one time. There were also 12 loaders, two excavators, and two or three bulldozers.

On Wednesday evening, workers finished the embankment required for the bridge abutments. They also hauled in asphalt milling for the embankment. About 560 tons of asphalt were needed to replace the roadway.

On Thursday morning, a 3-inch asphalt lift was laid and, later, another 4-inch lift was laid. The final 2-inch lift was in place by midnight Thursday, for a total of 9 inches of asphalt pavement. Cooler weather aided the asphalt placement to run ahead of schedule. Also on Thursday, concrete riprap was laid to stabilize the canal banks.

On Friday, the guardrail was placed. After some finishing touches, I-80 was completed and opened Friday at 8:00 p.m. Mountain Standard Time, two days before the one-week target. This was attributed to the extraordinary cooperation and teamwork between the contractors. The final repair cost was $499,736.37, less than half the $1-million estimate.

Another amazing aspect of the emergency construction project was its perfect safety record, both on the job site and along the detour routes. No accidents occurred during the round-the-clock intense interaction among contractors, construction crews, and state maintenance crews, where the hub of major activity was confined to within 1,000 feet and man-hours were at 2,500 to 3,000 over the work period. Interstate traffic was detoured for seven days onto two different two-lane, secondary, rural highways. Although a truck driver was killed during the flooding when the bridge approaches initially were swept away, there were no major safety incidents along the detour routes. 


Mary Jo Hall represents the Nebraska Department of Roads.

Reprinted from Better Roads Magazine
May 2003

 

Click Here to return to article index

Copyright © 2003 James Informational Media, Inc.
All rights reserved.

Home/Site Map
 
Buyers Guide
Supplier/Equipment
Information
Products
Top Products & More!
Industry Links
Associations, Suppliers,
DOT's, Counties
Article Archive
A popular Starting Point
Articles and News
Event Calendar
Trade Shows/Exhibits
& Events
RoadFax Forms
On-Line inquiry form
Advertising
Rate Card,
Advertising Information
Circulation
Subscription Form
Editorial
Editorial Calendar,
Submission Guidelines
Search  Classifieds Contact Us