|
With use
As the Interstate system grew and traffic
numbers began to increase steadily, bridge design, materials, and
construction methods had to change to keep pace.
Problems encountered brought about many of the
solutions developed in the industry.
Bridge deterioration, and particularly deck
deterioration, from salt was one of the earliest problems to be faced. This led to research of ways to control salt
penetration, Power says. First impermeable decks with epoxy-coated re-bars
were developed to prevent early deck deterioration and then impermeable deck
joints were developed to prevent salt deterioration to other parts of the
structure below.
Instead of the original simple spans with joints
that allowed deck drainage and salt to pass through to deteriorate piers,
designers began to use sealed joints or to eliminate them from the design
altogether by designing continuous structures.
Fatigue problems pushed for better bridge design,
too, Power says.
Originally, steel-welded designs were used as
welding replaced riveting as the most economical way of fabricating steel
girders. But welded girders with certain details developed cracks as heavy
truck traffic grew.
 |
| Workers place a beam on the I-5 Interstate
bridge over the Row River near Cottage Grove, Oregon. |
 |
| The OTIA III State Bridge Delivery Program
encourages using a mix of materials and construction methods. |
This brought about the study of fatigue behavior in
design at Lehigh and other institutions. Brittle fracture on long spans was
another aspect studied and the concept of a fracture-critical structure or
member was developed. To avoid fracture-critical structures where possible,
designers began to incorporate redundant load paths to provide safety if
fractures destroyed some paths.
Seismic research originally helped California build
flexible bridges that would better withstand earthquakes. As these designs
improved, they spread to other parts of the country where fault lines signal
their possible need. Methods of retrofitting older bridges to withstand
seismic events without collapse were developed and implemented.
As traffic continued to grow, bridge designs
themselves changed. A key direction was more lanes and longer spans, says
Power. Changes were implemented to accommodate not only more vehicles but to
increase the load-carrying ability as America switched from rail to truck
haulage. Added lanes also meant wider bridges.
Overpass piers were moved away from road shoulders
both for safety and to allow for future widening.
Longer girders were developed, including longer
precast prestressed concrete girders.
Materials change
High-performance steel and high-performance concrete
developments made the longer spans and shallower girders more feasible,
Power says. This provided both economy and lower bridge profiles.
Better materials and longer life became an industry
theme.
Make it quick
In recent years, most Interstate bridge work has
been replacement, rehabilitation, or widening — all while traffic keeps
rolling alongside.
As a Federal Highways Administration slogan says,
“Get in, get out; stay out.”
Rapid work led to new methods such as precast units
that can be set in place quickly. On some projects, a new bridge is build
adjacent to the original structure and then quickly rolled into place once
it’s completed.
Along with Rapid Construction to minimize traffic
disruption, Rapid project delivery is also the name of today’s bridge game,
Power says. Design-build is a perfect example. Rather than moving
laboriously from concept to design to bid to building, the design and
construction phases work together. The designer needs to understand the
construction method to give the contractor what’s needed. The bid comes up
front.
Beauty too
Context-sensitive design, which includes
aesthetics,public involvement and environmental awareness is current, too.
Many want signature bridges to give their city a unique look. Cable-stayed
bridges became popular as modern, practical, and aesthetic solutions,
pleasing the public.
Curved concrete girders and curved steel girders
allow construction of aesthetically and practical flyovers connecting
Interstate to Interstate.
Steel box girders and concrete segmental designs
provide aesthetic and practical options.
Cost volatility
New methods such as design-build may be pushed along
by today’s extreme volatility in prices, Power says.
On some major projects with traditional
design-bid-build methods, bids have come in at 20 to 50% over the engineers’
cost estimates.
Rapidly increasing costs of steel and concrete, as
well as site restrictions, and unique design details lie behind the problem.
In a volatile price market, bid price histories are no longer valid for
general cost estimating, particularly on special designs. Design-build can
be used to develop constructable concepts that stay within an owner’s
specified budget.
Funding for major projects is a real problem today,
with tolling, and other innovative financing methods, including public
private partnerships being frequently considered. State legislatures and
city authorities need to pass laws needed to use rapid-delivery methods, and
innovative financing where current restrictions are in place. The financing
situation demands it.
Alternative financing, including private-public
partnerships and the increased use of toll bridges may become matter-of-fact
solutions, rather than an occasional exception. |