| Better Bridges
FRP Improves Bridge Deck Life
Fiber-reinforced polymer shortened construction time and lengthened
deck life in West Virginia.
by David Holman Deitz
The use of fiber-reinforced polymers has become a more viable method
for improving the life-cycle costs of structural components. This is
particularly true for bridge decks in colder climates, such as West
Virginia, where deicing salts are used for snow and ice removal in winter
months.
The deicing salts increase the rate of reinforcement corrosion for more
typical reinforced concrete bridge decks, eventually resulting in bridge
deck replacement.
Since FRP bridge decks are immune to this type of corrosion, they can
potentially increase the service life of the bridge deck.
Other advantages of FRP bridge decks include their light weight and a
reduction in bridge deck construction time.
Disadvantages of FRP bridge decks include low modulus of elasticity
translating into increased deflections, greater initial expense, and
unfamiliarity to many engineers and constructors.
The site
Howell’s Mill Bridge carries County Route 1 over the Mud River in
Cabell County, West Virginia, near Huntington. The welded plate girder
bridge consists of two 120-foot continuous spans and supports the AASHTO
LRFD HL-93 live loading. The bridge deck is 32.5-feet wide and uses
reinforced concrete barriers. A 0.75-inch asphalt overlay was selected as
a riding surface. Howell’s Mill is a jointless bridge, continuous over
the pier. Abutments one and two are integral and semi-integral,
respectively.
The West Virginia Department of Transportation’s goal in selecting
Howell’s Mill Bridge for an FRP deck was to move towards making FRP a
more common material for use in bridge applications. To accomplish this
objective, WVDOT selected Howell’s Mill because it was a normal bridge
design application, rather that an ideal bridge for an FRP bridge deck. In
addition, they selected an engineering firm with experience in the design
of FRP structural components and one that was also involved in more
typical bridge designs in West Virginia.
|

|
|
Schematic shows the deck panel, including the
dual-cavity beam unit with adhesive bond line and the mirrored
unit. |
Design considerations
Initially, the project team wanted a common design that would provide
several different FRP bridge deck panel manufacturers the opportunity to
supply the deck panels, keeping with the goal of having the project
proceed as a normal bridge project. However, the characteristics of the
available deck panels, such as longitudinal stiffness, method of
connecting the deck to the girders, deck thickness, and so on, vary too
widely to allow for a common design. It was decided that a specific deck
panel would have to be selected prior to initiation of the design. The
panel selection was based largely on the amount of published test data
available for the panels that was directly applicable to the project.
The transverse girder spacing of 6.75 feet was selected for several
reasons. A review of previous projects showed that the FRP deck fabricator’s
panels could span 8 feet. However, there were few applications of the deck
with girders spaced greater than this. Rather than using a spacing of
greater than 8 feet, the project team decided to go with the 6.75-foot
girder spacing.
Second, a hydraulic analysis limited the height of the girders to 3.5
feet. The 6.75-foot girder spacing allowed the girders to meet this height
requirement and still be designed with more common plate sizes.
Once the girder spacing was selected and agreed upon by the design
engineer and the deck fabricator, it was up to the deck panel fabricator
to ensure that the deck panels could support the required vehicle loading.
Though the bridge design is based on the AASHTO LRFD HL-93 loading, the
design team felt that the deck should be capable of supporting an
additional load case equal to 1.25 times the HL-93 design truck. This is
similar to HS-25 truck loading currently used by many transportation
departments. It is possible a single-wheel load could control the design
of the deck, and the project team agreed that providing this overload
check was prudent.
The AASHTO LRFD code does not provide specific guidelines for the
distribution of wheel/axle loads to girders in the transverse direction
for bridges constructed with FRP deck panels. For cases not specifically
listed, AASHTO LRFD specifies that the lever rule be used to distribute
vertical deck loads to the girders. The lever rule assumes that the deck
is simply supported between girders, conservatively neglecting the
continuous beam behavior of the deck. The design team believed this type
of distribution was appropriate for the FRP deck panels.
Composite action between the girders and the FRP deck panels was
conservatively neglected in the design of the girders for the applicable
AASHTO LRFD strength requirements even though the FRP deck panels are
connected to the girders by shear studs. Neglecting the composite action
would ensure that the girders could support the required design loads
without relying on the strength of the FRP deck. Composite action was
considered for checks of the girders against the service, fatigue, and
deflection requirements provided in the AASHTO LRFD code. An effective
stiffness for the deck panels was taken from laboratory testing performed
by the deck panel manufacturer.
Even though the bridge deck was considered to be non-composite for
strength design, it is still necessary to check the shear studs for
strength requirements. The shear studs offer resistance to the applied
loading and a stud failure could result if an adequate number of studs are
not provided. Of course, the shear studs were checked for the fatigue
requirements since the bridge was designed as a composite structure for
this condition. This check would still be necessary even if the bridge was
designed as non-composite for fatigue. The studs will be present to
connect the bridge deck to the girders and, regardless of the design
assumptions, will act to transfer stresses between the two components.
Detailing
Howell’s Mill Bridge lies in a tangent section of County Route 1.
Though the project’s typical roadway cross section provided for a
crowned pavement surface in tangent sections, engineers decided to
maintain a constant 2% slope through the bridge. Fortunately, a right hand
curve was located immediately off the bridge allowing the 2% cross slope
to be implemented without resulting in driver discomfort.
If the deck cross section were crowned, the deck panels would have been
placed horizontally with 0% cross slope, and the crown would be built by
varying the thickness of the asphalt overlay. For Howell’s Mill, the
overlay would have varied by a thickness of almost 4 inches. This would
have increased the dead load of the bridge significantly, resulting in a
less efficient design.
Another benefit of the constant 2% cross slope is that water permeating
the overlay can drain more readily since the panels are sloped rather than
horizontal. Other FRP deck panel manufacturers can provide a roadway crown
by other means, such as building the crown into the deck itself or by
breaking the deck up into two pieces and splicing the pieces in the field.
Typical stay-in-place form angles of the girders are used to form the
haunch and support the FRP deck panels until the haunches are grouted. The
project specifications did not allow welding of stay-in-place form angles
to the top flange of the girder in any locations. The stay-in-place angles
are attached to the girders using a common form support angle, or strap,
spanning above the top flange. Once the deck panels are positioned on top
of the stay-in-place forms, shear studs are attached to the top flange of
the girder through stud pockets located along the top of each girder at a
2-foot spacing. The stud pocket size is adequate to attach the shear studs
using a standard stud gun. Finally, non-shrink grout is poured through the
stud pockets to form the haunch.
The connection of the deck to the abutment was made by passing bent #4
bars through the end void of the deck panel. The end void was filled with
concrete during construction of the backwall. It is important that the FRP
deck panel cut outs were large enough to allow the #4 rebar to pass
through the end void and to allow concrete to readily fill the end void
during construction.
The deck panels arrived on site with a skid-resistant top surface. This
skid-resistant surface both increases the bond between the deck and the
overlay and provides a non-slip surface during construction. A 0.75-inch
polymer asphalt overlay was selected for the bridge. The polymer asphalt
has a higher flexibility than more conventional asphalt concrete. The
increased flexibility is expected to increase the overlay’s resistance
to cracking in the negative moment region over the pier and to cracking
caused by thermal stresses.
Cost comparison
A cost comparison was made between the bridge with the FRP deck panels
and two conventional bridge types that would have been suitable for the
site. The first alternate is an adjacent prestressed concrete box beam
bridge made up of eight 42-inch-deep by 48-inch-wide box beams with a
5-inch-thick composite deck. The second is a welded steel plate girder
bridge with the same girder web depth and spacing as the proposed bridge,
but supporting an 8-inch-thick reinforced concrete deck.
Costs considered are for the superstructures only. Substructures for
the three bridges would be approximately the same. Costs studied for the
proposed bridge are actual project bid costs from the contractor who was
awarded the job. The costs for the two more conventional bridges were
estimated based on West Virginia average unit bid prices and information
provided by the contractor who bid the proposed FRP bridge. Results of the
study show that the initial cost of the proposed bridge with the FRP
bridge deck is approximately 2.4 times greater than the adjacent
prestressed concrete box beam bridge.
The bridge deck was constructed in a shorter amount of time than the
two other bridges. The fabricator estimated that the deck panels could be
placed in as little as two to three days, compared to the time required to
form, place concrete, and allow concrete to cure for the other two bridge
types. Though the time savings to the contractor are included in the
costs, the inconvenience to the public associated with the longer
construction time frame is not.
In addition, the cost comparison does not account for the longer
service life expected from the FRP deck panels compared to the
conventional reinforced concrete decks.
David Holman Deitz represents Palmer Engineering in Winchester,
Kentucky. This paper was presented as part of the 19th Annual
International Bridge Conference which took place in Pittsburgh,
Pennsylvania, June 10-12, 2002.
Reprinted from Better Roads Magazine
November 2002 |