|
Originally constructed in 1958, the I-5 section
consisted of 8 inches of reinforced, jointed concrete placed over an
aggregate base that was 9- to 12-inches thick. Since original
construction, the pavement has been overlaid with 3 to 6 inches of
asphalt concrete.
In places where the old pavement had been
thinned for grade purposes, there was evidence of extensive reflective
joint cracking. There were also instances of raveling and potholing,
along with joint faulting in the underlying concrete.
Though ODOT’s design for reconstruction of this
failing section was not necessarily intended to be a perpetual pavement,
conversations between Liz Hunt, pavement services engineer for ODOT, Jim
Huddleston of APAO, and Dr. Jim Lundy, professor of civil engineering at
OSU, led to the question of whether it could be classified as such. The
group agreed to have additional analysis conducted at OSU to test that
hypothesis.
Lundy said the design’s thickness and material
properties would enable it to be considered a perpetual pavement. The
analysis estimated fatigue resistance only, and determined that little
or no fatigue life would be consumed in this pavement through the course
of over 50 years of traffic. Lundy notes, however, that numerous other
variables in the construction process can impact the longevity of the
pavement structure. Those variables and other assumptions made during
analysis are among the items ODOT seeks to validate through data
collected over the next year at the site.
A layered approach
The 4.5-mile subsection of the project contains
the instrumentation that will be used for data collection. It is built
upon a base of rubblized concrete — material that was once part of the
original roadway that has been broken up for reuse as a pavement base.
The failed concrete was rubblized to provide more uniform support, and
to reduce or eliminate reflective cracking that can originate in
concrete joints.
Atop the rubblized concrete are 12 inches of
asphalt divided into three layers. The bottom two layers consist of
0.75-inch dense-graded mix, and the top layer consists of 0.75-inch
open-graded mix.
The bottom layer of asphalt is an 8-inch base
designed for fatigue resistance and durability. It was designed at 100
gyrations and the binder content was selected at 3% air voids instead of
the usual 4% that is targeted. The resulting asphalt content was 5.9%,
about one-half percent more than the layer immediately above it. The
higher binder content, coupled with a higher field density requirement,
ensures in-place air voids averaging nearly 5%. ODOT’s conventional base
design averages in-place air voids of about 7%.
Implementation of the rich bottom base was a
deviation from the original reconstruction design, and was proposed by
ODOT and APAO’s joint Quality Improvement Committee. The higher
binder content in the base will contribute to improved durability and
fatigue resistance, which are critical to the long-term survival of a perpetual
pavement.
The top 4 inches of the pavement structure
consist of two layers that are each 2-inches thick. The first is a
dense-graded Superpave mix with 5.4% asphalt content, and the second is
a wearing course. The wearing course is comprised of a 0.75-inch
open-graded mix. ODOT selected the open-graded wearing course for its
ability to reduce splash, spray, and road noise.
Comparing notes
A variety of measuring devices that will
potentially validate the analysis conducted at OSU were installed in the
4.5-mile segment of this project.
Gauges were inserted on top of the rubblized
concrete base to measure the strain at the bottom of the asphalt. One of
the industry standards for classification as a perpetual pavement is a
strain of 70 microstrain or less at the bottom of the asphalt layer.
OSU’s analysis determined that the vast majority of the strains on this
pavement would be below 70 microstrain. These gauges will allow direct
comparison of the measured strain to that predicted by the OSU analysis.
Temperature gauges were also installed in the
segment. The stiffness of asphalt is highly influenced by temperature,
and it is critical to understand how the temperature varies seasonally
within the pavement in order to make reliable predictions on bending and
strain. Analysis based on data collected from these instruments will
include review of performance from season to season and comparison of field results
to performance expectations established in the lab.
The project also includes a portable
weigh-in-motion site that will monitor truckloads as they cross. Data
collection will include truck weight and number of axles on the truck,
as well as axle configuration. Results will be used to relate axle load
and configuration to the measured strains.
What it means
Data from the I-5 project will be collected over
the course of the next year. In the short term, it will provide
measurement of the strain present in this particular project, and will
potentially validate performance expectations suggested by OSU’s
analysis.
“This project will enable us to refine our
material property inputs. We’ll have a better understanding of how they
vary with changes in temperature and moisture, and how they are affected
by different loading conditions. And of course, we’ll be able to refine
our models for predicting strain,” said Bruce Patterson, ODOT pavement
materials engineer.
“The whole country is moving toward
mechanistic-empirical design,” said Liz Hunt. “This data will help us
establish guidelines in Oregon for future perpetual pavement projects.”
|