|
The committee determined the following
specifications for each layer of the pavement buildup:
6-inch building platform: ODOT Item 304, a
highly crushed densely graded granular base, with under drains.
4-inch bottom — fatigue resistant layer: ODOT’s
large stone base mix, Item 302, made binder rich by designing it for 3%
air voids; 94 to 97% constructed density.
9-inch middle — high modulus layer: ODOT’s large
stone mix, Item 302, using a PG 64-22 asphalt binder; target density 93
to 96%.
3.25-inch top — sacrificial layer composition:
— 1.75-inch intermediate course: ODOT 19-mm
Superpave, Type A, with PG 76-22M polymer modified binder; target
density 93 to 97%.
— 1.5-inch wearing course: ODOT 12.5-mm stone
mastic asphalt with a PG 76-22M polymer modified binder; target density
93 to 97%.
Validating the design concept
The U.S. 30 demonstration project is under
construction and is expected to open to traffic in the fall of 2005. After
construction, validation of the thickness design concept is the final step.
To accomplish this, ODOT has awarded three research contracts to Ohio
University to evaluate the perpetual pavement.
The objective of the first research project is to
determine the mechanical properties of the materials used in the
construction of the U.S. 30 test pavement. In this project, the researcher
is to review the design assumptions used to determine the pavement buildup
and identify the mechanical properties needed to validate the design
procedures. A sampling and testing plan was developed to determine the
mechanical properties of all pavement layers needed to validate the design
procedure. ODOT, the paving subcontractor, Shelly and Sands Inc., and Ohio
University researchers collect the necessary samples as construction
progresses.
The second research project seeks to collect
environmental and load response data from test sections on the U.S. 30
demonstration project by developing a pavement instrumentation plan and
installing the instrumentation during construction of the project. Being
measured are pavement and subgrade temperature, aggregate base and subgrade
moisture, frost depth in the aggregate base and subgrade, groundwater table,
strain and deflection in the asphalt due to load, pressure at the interface
between the aggregate base and subgrade, and climate. The Ohio University
research team has been installing the instrumentation as construction
proceeds.
The third and final research project validates the
perpetual pavement design procedures. The predicted pavement response will
be compared to the actual field response under traffic loads. The analysis
uses the mechanical properties of materials determined in the construction
of the test pavement, the load response data collected from the instrumented
test sections, coring data supplied by ODOT, and any specification
deviations to the materials and/or construction methods.
While the U.S. 30 demonstration project was still
being designed, an opportunity presented itself to use the perpetual
pavement design on a section of I-77 that was already under construction.
The paving subontractor on that project, Northstar Asphalt, proposed using
the perpetual pavement design as a no-cost change on the project and the
change was accepted by ODOT. Ohio University conducted a research effort on
the Interstate 77 project that is similar to that proposed for the U.S. 30
project. In August, 2003, a test section consisting of 6 inches of
dense-graded aggregate base, 13 inches of bituminous aggregate base, and a
1.75-inch intermediate surface layer was instrumented. Instrumentation
included strain gauges, pressure cells, and thermocouples. In December 2003,
data was collected from these sensors in response to a load applied using an
ODOT single-axle truck having an axle weight of 26,000 pounds. Pavement
response indicated that the strains at the bottom of the asphalt layer were
approximately half of what is considered to be a maximum design value — 70
microstrain.
A whole lot more
In addition to the thickness design methodology,
ODOT is seeking to evaluate other attributes of perpetual pavement that
affect management decisions. The U.S. 30 demonstration project will be
observed through 2006, with extensive data collected in four categories —
cost, safety, user delay, and ride and condition. The evaluation criteria
developed by ODOT address every significant measurable element needed for
determining the manageability of perpetual pavement.
Project Evaluation Criteria
Cost:
-
Initial construction cost
-
Rehabilitation cost
-
Force account maintenance (hours and cost)
-
Salt usage (hours and cost)
-
Truck fuel usage
-
Pavement marking costs
-
Lighting
Safety:
User Delay:
Ride & Condition:
Long-lived asphalt pavements aren’t new to Ohio. The
state has enjoyed very long life from its conventionally designed asphalt
structural bases. As the perpetual pavement design protocols are refined for
Ohio conditions and materials, it is expected that long-lived pavements will
become more reliable and economical than ever before.
“Ohio has a long history of long-lived, full-depth,
and deep-strength asphalt pavements; so, we expect perpetual pavement to
receive a superior evaluation in every category,” says Fred Frecker,
Executive Director of Flexible Pavements of Ohio. “We have a high degree of
confidence that perpetual pavement is a cost-effective way for Ohio to
maintain a high level of user satisfaction.”
Engineers of the famed AASHTO Road Test
revolutionized pavement engineering with the development of the
service-ability concept. They defined successful pavement performance as
that which serves the user. The Ohio DOT is right on point with its pursuit
of perpetual pavement research. Perpetual pavements are built to serve the
user by providing inexhaustible structural life with only the need to
occasionally refurbish the wearing surface. The research effort in Ohio is
sure to return dividends to Ohio’s motorists, and provide additional data to
the ever-increasing body of knowledge being accrued on the national level. |