September 2002
Back to Article Index

Road Science

Complexity Makes Major Projects Challenging

From Boston’s Big Dig to California’s need to add earthquake-resistant features to bridges, agencies and contractors meet those challenges.

by Ruth W. Stidger, Editor-in-Chief

What makes a challenging project? Some engineers say it is complexity. If so, today’s bridge and road projects will become ever-more challenging.

Many of these big and tough projects are built in urban areas, where buildings and other infrastructure already occupy every square foot of land. Others call for new technologies to help solve the problems that make them necessary.

Agencies, engineering companies, and contractors work together as a team on these projects more than on any other type of work. It’s absolutely necessary because the work is just too daunting to go it alone.

New materials, designs, and techniques all find their place in today’s most challenging projects.

Boston Continues Its Big Dig

Boston’s $15-billion Central Artery/Tunnel project, fondly called the Big Dig, stands as one of the most daring projects in history.

To deal with its massive traffic problems, the Metropolitan Transit Authority started the project that, when finished, will include an eight- to-10-lane underground expressway, a two-bridge crossing of the Charles River, and a tunnel under South Boston and Boston Harbor to Logan Airport, including the four-lane Ted Williams Tunnel.

The elevated six-lane highway called the Central Artery that it replaces was built in 1959 and could carry about 75,000 vehicles comfortably. With 200,000 vehicles crowding the road daily, traffic congestion problems were rampant.

“Traffic crawls for more than 20 hours each day,” says the Web site covering the Big Dig. “The accident rate on the deteriorating elevated highway is four times the national average for urban Interstates. The same problem has plagued the two tunnels under Boston Harbor between downtown Boston and East Boston/Logan Airport. Without major improvements to the Central Artery and the harbor crossings, Boston could expect a stop-and-go traffic jam for up to 16 hours a day — every waking hour — by 2010.

“The annual cost to motorists from this congestion — in terms of an elevated accident rate, wasted fuel from idling in stalled traffic, and late delivery charges — is estimated to be $500 million.

The solution, the Central Artery/Tunnel Project, scheduled for completion in 2004, includes two major components:

1. The six-lane elevated highway will be replaced with an eight- to 10-lane underground expressway directly beneath the existing road. At its northern limit, there will be a 14-lane, two-bridge crossing of the Charles River.

After the underground road is finished, the crumbling elevated highway will be demolished and replaced by development and open space.

2. I-90, the Massachusetts Turnpike, will be extended from south of downtown Boston through a tunnel under South Boston and Boston Harbor to Logan Airport. The first link, the four-lane Ted Williams Tunnel under the harbor, opened to limited traffic in 1995.

Project Details

To put these highway improvements in the ground in a city like Boston amounts to one of the largest, most technically difficult and environmentally challenging infrastructure projects ever undertaken in the United States, project engineers report.

The project covers 7.8 miles of highway, or 161 lane miles. About half of this is in tunnels.

The project’s contractors will place 3.8 million cubic yards of concrete and excavate over 16 million cubic yards of soil.

The larger of the two bridges, the Leonard P. Zakim Bunker Hill Bridge, is a 10-lane, cable-stayed hybrid bridge. It is the widest ever built and the first to use an asymmetrical design.

Four major highway interchanges connect the new roadways with existing highways.

At Logan, a new interchange will carry traffic between I-90 and Route 1A as well as onto the airport road system.

The underground interchange in South Boston moves traffic between I-90 and the waterfront/convention center area.

A new interchange will also connect I-93 north of the Charles River to the Tobin Bridge, Storrow Drive, and the new underground highway.

At the south end of the underground road, an interchange between I-90 and I-93 is being completely rebuilt on six levels. Two of these are subterranean to connect with the underground Central Artery.

An interchange at Massachusetts Avenue on I-93 has been rebuilt.

A Tough Site

The project’s unique challenge is the fact that it is being built in the middle of Boston. Work of this magnitude has never been tried in the midst of an urban area. And, the contractors must maintain traffic capacity and access to residents and businesses throughout the work.

Mitigation efforts account for a quarter of the total budget. This includes old road demolition, creation of open land, and the new Spectacle Island, where project dirt is capping an abandoned dump in Boston Harbor.

Work started 11 years ago. About 80% of the construction has been completed.

A bridge across the Charles River (pictured) connecting I-93 in Charlestown with Leverett Circle and Storrow Drive opened in 1999.

The I-90 Logan Airport extension through South Boston will open this month.

Northbound lanes of the underground highway will open in November, while the southbound lanes are slated for use in late 2003.

Project completion will be in late 2004, with the demolition of the elevated highway and restoration of the surface.

The Central Artery/Tunnel Project is owned and managed by the Massachusetts Turnpike Authority and is part of the Metropolitan Highway System. Design and construction management consulting is provided by Bechtel/Parsons Brinckerhoff, a joint venture of Bechtel Corporation of San Francisco and Parsons Brinckerhoff Quade & Douglas, Inc. of New York.


Construction Timeline

1982: Planning for the Central Artery Tunnel Project began.

1991: Construction of the Ted Williams Tunnel and a bypass road through South Boston began.

1995: Ted Williams Tunnel was completed.

1999: Leverett Circle Connector Bridge over the Charles River opened.

2002: I-90/Massachusetts Turnpike extension opens in three phases; northbound Central Artery I-93 underground road and Leonard P. Zakim Bunker Hill Bridge completed by the end of the year.

2003: Southbound Central Artery I-93 underground road open at the end of the year.

2004: Project completed, including demolition of elevated Central Artery and restoration of the surface.

 

Facts About Carrying Traffic

1. Downtown Central Artery I-93 will carry 245,000 or more vehicles a day with ease.

2. I-93 will be up to 10-lanes wide and safely underground. It will have fewer on- and off-ramps than the elevated road and a new network of surface streets.

3. The Ted Williams Tunnel will carry more than 90,000 vehicles a day.

4. Boston’s carbon monoxide levels will drop about 12% from the decrease in stalled traffic.


Storrow Drive Bridge

The Big Dig’s Storrow Drive Connector Bridge was designed with steel for cost and constructability purposes, according to Sena T. Kumarasena, P.E. and Raymond J. McCabe, P.E., with the HNTB Corporation.

When considering materials, Tampa Steel suggested fabricating the entire 830-foot-long box girder in sections and delivering them by ocean-going barge.

Key design challenges, according to Kumarasena and McCabe were:

1. The exceptional size and weight of the box-girder sections.

2. Weak and variable rock conditions adding to needed foundation design measures.

3. Potentially liquefiable soil, especially on the south bank.

4. Visual harmony with abutting structures and with the mainline cable-stayed bridge, also crossing the Charles River.

The use of the single box girder with floor-beam cantilevers was chosen for aesthetic reasons, Kumarasena and McCabe say. Tampa Steel provided nine field sections, which were spliced on site.

A curved steel multi-box girder viaduct at the south interface and a concrete segmental viaduct at the north interface abut the bridge. Modular expansion joints were used between the bridge and both interfaces.

Main piers are founded on 8-foot-diameter shape-drilled rock sockets.

The drilled shafts were designed to hold against forces developed by lateral spreading of post-liquefied soils. At the south-end pier, a permanent steel outer casing adds even more reinforcement to the drilled shafts.

A 1-inch-thick, 4,500-psi concrete deck slab acts compositely with the main box girder, the transverse floor beams, and the longitudinal fascia girders.

The contractor for the $22.3-million bridge was Daniel O’Connell, Holyoke, Massachusetts. HNTB designed and oversaw construction.


Early Opener

The Ted Williams Tunnel under Boston Harbor opened early in the construction project.

The 0.75-mile underwater section of the $1.3-billion, 1.6-mile tunnel was built with steel tube sections that were sunk into a trench on the harbor floor and connected.

Traffic has been limited until the tunnel is fully connected to the rest of the project.

Reprinted from Better Roads Magazine
September 2002

 

Click Here to return to article index

Copyright © 2002 James Informational Media, Inc.
All rights reserved.

Home/Site Map
 
Buyers Guide
Supplier/Equipment
Information
Products
Top Products & More!
Industry Links
Associations, Suppliers,
DOT's, Counties
Article Archive
A popular Starting Point
Articles and News
Event Calendar
Trade Shows/Exhibits
& Events
RoadFax Forms
On-Line inquiry form
Advertising
Rate Card,
Advertising Information
Circulation
Subscription Form
Editorial
Editorial Calendar,
Submission Guidelines
Search  Classifieds Contact Us